PlanningRegister.ie
Cork County Council · 18/5573

Farranthomas Newcestown Bandon Co. Cork

Approved in Sept 2018. Building started in 2018.

  1. 18 Jun 2018Received
  2. 8 Aug 2018Conditional
  3. 18 Sept 2018Final approval
  4. 3 Nov 2018Building started
Status
Building startedi
Decision
Conditional · 8 Aug 2018
Council
Cork County Council
Type
PERMISSION
Site
3,460 m²

Live near Farranthomas Newcestown Bandon Co. Cork?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

Construction of dwellinghouse (change of plan from that granted under Pl. Reg. 15/4786)

Planning details

Reference
18/5573
Local authority
Cork County Council
Status
Commenced · register status “APPLICATION FINALISED”
Received
18 Jun 2018
Observations close
23 Jul 2018 (closed 3012 days ago)
Decision due
13 Aug 2018 · decided 8 Aug 2018
Decision
Conditional on 8 Aug 2018
Site area
3,460 m² from the mapped boundary, not the council's figure

Nearby 4 · 500 m · 5 years

Explore this area on the map →

Building started

  • 3 Nov 2018 · Builder told the council work was starting (opted out of the finish sign-off) CN0045582CC

Protections nearby 250 m

  • NIAH-recorded building · 1
    St Patrick's Church Of Ireland Church

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

18/5573 is a planning application to Cork County Council for construction of dwellinghouse (change of plan from that granted under Pl. Reg. 15/4786), received on 18 Jun 2018; permission was granted with conditions on 8 Aug 2018.