Munnig South Skibbereen Co Cork
Approved in Jun 2019. Building started in 2022.
- 28 Dec 2018Received
- 17 May 2019Conditional
- 24 Jun 2019Final approval
- 21 Mar 2022Building started
- Status
- Building startedi
- Decision
- Conditional · 17 May 2019
- Council
- Cork County Council
- Type
- PERMISSION
- Site
- 2,348 m²
Live near Munnig South Skibbereen Co Cork?
Everything else planned on your street, in one report.
Check my streetWhat’s proposed
Retain and complete two storey extension to rear of existing dwelling and retention of increased eaves and ridge height to roof of existing dwelling together with retention of demolition works on two lean-to-side annexes of existing dwelling, permission to construct new lean-to-side annex, construction of new site entrance, installation of new domestic effluent treatment plant, including all site development works to facilitate the foregoing works
Planning details
- Reference
- 18/818
- Local authority
- Cork County Council
- Status
- Commenced · register status “APPLICATION FINALISED”
- Received
- 28 Dec 2018
- Observations close
- 5 Feb 2019 (closed 2812 days ago)
- Decision due
- 21 May 2019 · decided 17 May 2019
- Decision
- Conditional on 17 May 2019
- Site area
- 2,348 m² from the mapped boundary, not the council's figure
Nearby 3 · 500 m · 5 years
Homes nearby
Building started
- 21 Mar 2022 · Builder told the council work was starting (opted out of the finish sign-off) CN0087180CC
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
18/818 is a planning application to Cork County Council for retain and complete two storey extension to rear of existing dwelling and retention of, received on 28 Dec 2018; permission was granted with conditions on 17 May 2019.