Ballynona North Dungourney Co. Cork
Approved in Aug 2019. The approval ran out in 2024.
- 15 Mar 2019Received
- 17 Jul 2019Conditional
- 23 Aug 2019Final approval
- 23 Aug 2024Approval ran out
Earlier approval here ran out with no sign of building: 14/5024 (2015)
- Status
- Approved
- Decision
- Conditional · 17 Jul 2019
- Council
- Cork County Council
- Type
- PERMISSION
- Site
- 39.52 ha
Live near Ballynona North Dungourney Co. Cork?
Everything else planned on your street, in one report.
Check my streetWhat’s proposed
The expansion of the existing maturation warehouse facility and all ancillary site development works. The proposed development includes 60 no. maturation warehouses, which will be constructed in 30 no. blocks of 2 warehouses and 3 no. ESB substations. Ancillary site development works include landscaping, tree felling, berming, fencing, settlement basin and a surface water attenuation pond. Access to the expanded maturation facility will be via the existing entrance and access road from the L3800. Emergency access will be provided via the existing gated entrance from the L7693. An Environmental Impact Assessment Report (EIAR) has been prepared and will be submitted to the Planning Authority with the application. The proposed development is for modifications to an establishment to which the Major Accident Directive applies
Planning details
- Reference
- 19/4641
- Local authority
- Cork County Council
- Status
- Granted with conditions · register status “APPLICATION FINALISED”
- Received
- 15 Mar 2019
- Observations close
- 19 Apr 2019 (closed 2730 days ago)
- Decision due
- 18 Jul 2019 · decided 17 Jul 2019
- Decision
- Conditional on 17 Jul 2019
- Proposed development
- The expansion of the existing maturation warehouse facility and all ancillary site development works. The proposed development includes 60 no. maturation warehouses, which will be constructed in 30 no. blocks of 2 warehouses and 3 no. ESB substations. Ancillary site development works include landscaping, tree felling, berming, fencing, settlement basin and a surface water attenuation pond. Access to the expanded maturation facility will be via the existing entrance and access road from the L3800. Emergency access will be provided via the existing gated entrance from the L7693. An Environmental Impact Assessment Report (EIAR) has been prepared and will be submitted to the Planning Authority with the application. The proposed development is for modifications to an establishment to which the Major Accident Directive appliesAs published by the register.
- Site area
- 39.52 ha from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Nearby 1 · 500 m · 5 years
Zoning
Not zoned in the current plan.
Protections nearby 250 m
No mapped flood area nearby.
- Recorded monument · 4
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 18 Sept 2026, 15:44 | open |
Summary
19/4641 is a planning application to Cork County Council for the expansion of the existing maturation warehouse facility and all ancillary site, received on 15 Mar 2019; permission was granted with conditions on 17 Jul 2019.