Cork County Council · 20/594
"The Strand" Ballydonegan Allhies Beara, Co. Cork
Approved, built and signed off.
- 23 Oct 2020Received
- 30 Oct 2020Building started
- 15 Dec 2020Conditional
- 26 Jan 2021Final approval
- 31 Aug 2021Signed off
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
- Status
- Building started
- Decision
- Conditional · 15 Dec 2020
- Council
- Cork County Council
- Type
- PERMISSION
- Site
- 3,725 m²
Live near "The Strand" Ballydonegan Allhies Beara?
Everything else planned on your street, in one report.
Check my streetWhat’s proposed
Permission for construction of extension to dwelling and all associated site works
Planning details
- Reference
- 20/594
- Local authority
- Cork County Council
- Status
- Commenced · register status “APPLICATION FINALISED”
- Received
- 23 Oct 2020
- Observations close
- 27 Nov 2020 (closed 2139 days ago)
- Decision due
- 17 Dec 2020 · decided 15 Dec 2020
- Decision
- Conditional on 15 Dec 2020
- Proposed development
- Permission for construction of extension to dwelling and all associated site worksAs published by the register.
- Site area
- 3,725 m² from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Nearby 1 · 500 m · 5 years
Homes nearby
Building started
- 17 May 2021 · Builder told the council work was starting (seven-day notice) SN0006080LS
- 30 Oct 2020 · Builder told the council small works were starting CN0069757TT
Zoning
Not zoned in the current plan.
Protections nearby 250 m
No mapped flood area nearby.
- Recorded monument · 2
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 18 Sept 2026, 15:44 | open |
Summary
20/594 is a planning application to Cork County Council for permission for construction of extension to dwelling and all associated site works, received on 23 Oct 2020; permission was granted with conditions on 15 Dec 2020.