PlanningRegister.ie
Cork County Council · 20/6891

Lysaghtstown Midleton Co. Cork

  1. 13 Jan 2021Received
  2. 19 Feb 2021Conditional permission
  3. 25 Mar 2021Final grant
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Granted with conditions
Decision
Conditional permission · 19 Feb 2021
Council
Cork County Council
Type
Permission
Site
8.07 ha

What’s proposed

A 10 year planning permission for a solar farm consisting of circa 14,600 m2 of solar panels on ground mounted frames, 2 no. single storey electrical inverter/transformer stations, battery storage container, battery control unit, security fencing, satellite pole, CCTV, access tracks, upgrade to existing agricultural field entrance, temporary construction compound, landscaping and all associated ancillary development works. The proposed development is a change of plan to part of the solar farm previously permitted under Cork County Council planning reference 18/6769 and will provide for the omission of the previously permitted 38kV substation and a net decrease in overall panel area of circa 10,800 m2 from that permitted under 18/6769. Construction and operational access will be via the L-7634. The operational lifespan of the solar farm will be 35 years. A Natura Impact Statement (NIS) has been prepared and will be submitted to the Planning Authority with the application

20/6891 is a planning application to Cork County Council for a 10 year planning permission for a solar farm consisting of circa 14,600 m2 of solar, received on 13 Jan 2021; permission was granted with conditions on 19 Feb 2021.

Planning details

Reference
20/6891
Local authority
Cork County Council
Status
Granted with conditions · register status “Application Closed
Received
13 Jan 2021
Observations close
17 Feb 2021 (closed 2040 days ago)
Decision due
22 Feb 2021 · decided 19 Feb 2021
Decision
Conditional permission on 19 Feb 2021
Proposed development
A 10 year planning permission for a solar farm consisting of circa 14,600 m2 of solar panels on ground mounted frames, 2 no. single storey electrical inverter/transformer stations, battery storage container, battery control unit, security fencing, satellite pole, CCTV, access tracks, upgrade to existing agricultural field entrance, temporary construction compound, landscaping and all associated ancillary development works. The proposed development is a change of plan to part of the solar farm previously permitted under Cork County Council planning reference 18/6769 and will provide for the omission of the previously permitted 38kV substation and a net decrease in overall panel area of circa 10,800 m2 from that permitted under 18/6769. Construction and operational access will be via the L-7634. The operational lifespan of the solar farm will be 35 years. A Natura Impact Statement (NIS) has been prepared and will be submitted to the Planning Authority with the application
As published by the register.
Site area
8.07 ha from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 4 applications within 500 m in the last 5 years

Explore this area on the map →

Appeal

Not appealed.

Commencement

No commencement notice matched to this reference.

    Zoning at the site

    No zoning objective covers this site in the current plan.

    Designations within 250 m

    No OPW flood extent nearby.

    No other designation nearby.

    Provenance

    Register row from the national planning applications feed (NPAD), fetched 18 Sept 2026, 15:44 (store id 324279). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: https://planning.agileapplications.ie/corkcoco/application-details/?ref=20/6891.

    Source: npad · fetched 18 Sept 2026, 15:44
    SourceLicenceFetchedLink
    npadCC-BY-4.018 Sept 2026, 15:44open