Gortnagross Mallow Co. Cork
Approved in Apr 2021.
- 26 Feb 2021Received
- 20 Apr 2021Unconditional
Planning details
- Status
- Approved
- Decision
- Unconditional · 20 Apr 2021
- Reference
- 21/4498
- Type
- EXTENSION OF DURATION
- Received
- 26 Feb 2021
- Site
- 15.32 ha
What’s proposed
A 5 MW solar farm comprising approximately 22,200 photovoltaic panels on ground mounted frames within a site area of 15.38 hectares, 2 no. single storey inverter/transformer stations, 1 no. single storey delivery station, security fencing, CCTV and all associated ancillary development works. - Extension of duration of permission granted under planning reference: 15/7003
2 other applications within 500 m in the last year
Open the reportNearby 2 · 500 m · 12 months
Homes nearby
Zoning
Protected high-amenity landscape. Development is resisted to preserve the character of the area.
Protections nearby 250 m
- Recorded monument · 3
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
21/4498 is a planning application to Cork County Council for a 5 MW solar farm comprising approximately 22,200 photovoltaic panels on ground mounted, received on 26 Feb 2021; permission was granted on 20 Apr 2021.