PlanningRegister.ie
Cork County Council · 21/4516

Kerrygold Park Mitchelstown Co. Cork

Approved in 2021. Approval ran out in 2026.

  1. 2 Mar 2021Received
  2. 24 Jun 2021Conditional
  3. 24 Jun 2026Approval ran out

Earlier approval here ran out with no sign of building: 19/6855 (2020), 14/5908 (2014)

Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Approved
Decision
Conditional · 24 Jun 2021
Council
Cork County Council
Type
PERMISSION
Site
2.61 ha

Live near Kerrygold Park Mitchelstown Co. Cork?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

An extension (4364m2) to the existing Butter Processing Facility (6146m2) for the manufacture, packaging and distribution of Butter products permitted by Cork County Council planning application references 145908 & 196855. The proposal will comprise: extensions adjoining the main building ranging from c.9.35m to 18.85m in height consisting of; c.330m2 of office/ancillary accommodation arranged over two storeys, c.1,219m2 of ground floor production space, with c. 331m2 of first floor / mezzanine production space, c.1,987m2 of single storey storage/distribution space, enclosed plant space c.118m2 with open plant area above of c. 7m in height and a single storey liquid ingredients intake building extension c.68m2 with open plant area above of c. 9.5m in height. 7 no. new liquid storage silos of c.15 m in height with associated access platforms. A new single storey maintenance store c. 103m2 of c.5.5m in height. A new enclosure for existing wastewater pre-treatment equipment c.112m2 of c. 4.0m in height. A new enclosure to the existing process water storage tank of c.96m2 of c. 5.5m in height. Relocation of existing liquid storage unit. Existing external signage relocated on western elevation. 36 no. new car parking spaces in a new parking area containing 72 space of which 36 are displaced by the proposed extension, 17 no. new bicycle parking spaces, 4 no. new motorcycle parking spaces. Landscaping, hardstandings, underground services and ancillary works. All on site area of 2.62 Ha. All access to and from the site will remain by way of the existing access road to Castlefarm from the N73 (Kildorrery) roundabout. The application relates to a development which is located on a site which operates under Industrial Emissions License P0404-02. The environmental Impact Assessment Report and Natura Impact Statement will be submitted to the Planning Authority with the application

Planning details

Reference
21/4516
Local authority
Cork County Council
Status
Granted with conditions · register status “APPLICATION FINALISED”
Received
2 Mar 2021
Observations close
6 Apr 2021 (closed 2009 days ago)
Decision due
6 Jul 2021 · decided 24 Jun 2021
Decision
Conditional on 24 Jun 2021
Proposed development
An extension (4364m2) to the existing Butter Processing Facility (6146m2) for the manufacture, packaging and distribution of Butter products permitted by Cork County Council planning application references 145908 & 196855. The proposal will comprise: extensions adjoining the main building ranging from c.9.35m to 18.85m in height consisting of; c.330m2 of office/ancillary accommodation arranged over two storeys, c.1,219m2 of ground floor production space, with c. 331m2 of first floor / mezzanine production space, c.1,987m2 of single storey storage/distribution space, enclosed plant space c.118m2 with open plant area above of c. 7m in height and a single storey liquid ingredients intake building extension c.68m2 with open plant area above of c. 9.5m in height. 7 no. new liquid storage silos of c.15 m in height with associated access platforms. A new single storey maintenance store c. 103m2 of c.5.5m in height. A new enclosure for existing wastewater pre-treatment equipment c.112m2 of c. 4.0m in height. A new enclosure to the existing process water storage tank of c.96m2 of c. 5.5m in height. Relocation of existing liquid storage unit. Existing external signage relocated on western elevation. 36 no. new car parking spaces in a new parking area containing 72 space of which 36 are displaced by the proposed extension, 17 no. new bicycle parking spaces, 4 no. new motorcycle parking spaces. Landscaping, hardstandings, underground services and ancillary works. All on site area of 2.62 Ha. All access to and from the site will remain by way of the existing access road to Castlefarm from the N73 (Kildorrery) roundabout. The application relates to a development which is located on a site which operates under Industrial Emissions License P0404-02. The environmental Impact Assessment Report and Natura Impact Statement will be submitted to the Planning Authority with the application
As published by the register.
Site area
2.61 ha from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 5 · 500 m · 5 years

Explore this area on the map →

Homes nearby

Zoning

C2.1 — Economic development and employment

Zoned for employment uses. Housing is not the intended use here.

M4 — Major town centre

The main town centre — retail, offices, civic uses, apartments.

Protections nearby 250 m

No mapped flood area nearby.

  • NIAH-recorded building · 3
    farmyard complex; graveyard/cemetery
  • Recorded monument · 7
    Ritual site - holy well; Castle - unclassified

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: npad · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
npadCC-BY-4.018 Sept 2026, 15:44open
Summary

21/4516 is a planning application to Cork County Council for an extension (4364m2) to the existing Butter Processing Facility (6146m2) for the, received on 2 Mar 2021; permission was granted with conditions on 24 Jun 2021.