PlanningRegister.ie
Cork County Council · 21/6638

Clogheen Mourneabbey Mallow Co. Cork

Approved in Feb 2022. Building started in 2022.

What’s proposed

To construct a dwelling and detached domestic garage, install a wastewater treatment unit and raised percolation area and carry out of all associated site works

  1. 28 Sept 2021Received
  2. 20 Dec 2021Conditional
  3. 3 Feb 2022Final approval
  4. 5 May 2022Building started

Planning details

Status
Building startedi
Decision
Conditional · 20 Dec 2021
Reference
21/6638
Received
28 Sept 2021
Site
1.33 ha

Every application, appeal and deadline within 500 m

Get the full report

Explore this area on the map →

Building started

  • 5 May 2022 · Builder told the council work was starting (opted out of the finish sign-off) CN0088796CC

Protections nearby 250 m

  • Recorded monument · 1
    R113961
Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

21/6638 is a planning application to Cork County Council for to construct a dwelling and detached domestic garage, install a wastewater treatment, received on 28 Sept 2021; permission was granted with conditions on 20 Dec 2021.