Approved in Jan 2022. No sign of building yet.

  1. 1 Oct 2021Received
  2. 23 Nov 2021Conditional
  3. 5 Jan 2022Final approval
  4. 5 Jan 2027Approval runs out
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Approved
Decision
Conditional · 23 Nov 2021
Council
Cork County Council
Type
PERMISSION
Site
8,861 m²

Live near Reenacappul Ahakista Bantry Co. Cork?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

Permission for the following: (i) construction of dwelling house, (ii) installation of wastewater treatment system, (iii) construction of detached domestic garage and (iv) associated site works

Planning details

Reference
21/675
Local authority
Cork County Council
Status
Granted with conditions · register status “APPLICATION FINALISED”
Received
1 Oct 2021
Observations close
5 Nov 2021 (closed 1799 days ago)
Decision due
25 Nov 2021 · decided 23 Nov 2021
Decision
Conditional on 23 Nov 2021
Proposed development
Permission for the following: (i) construction of dwelling house, (ii) installation of wastewater treatment system, (iii) construction of detached domestic garage and (iv) associated site works
As published by the register.
Site area
8,861 m² from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 15 · 500 m · 5 years

Show all 15

Explore this area on the map →

Homes nearby

Zoning

Not zoned in the current plan.

Protections nearby 250 m

No mapped flood area nearby.

  • Recorded monument · 1
    R100451

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: npad · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
npadCC-BY-4.018 Sept 2026, 15:44open
Summary

21/675 is a planning application to Cork County Council for permission for the following: (i) construction of dwelling house, (ii) installation of, received on 1 Oct 2021; permission was granted with conditions on 23 Nov 2021.