Cork County Council · 21/872
Allihies Beara Co. Cork
Approved in Mar 2022. Building started in 2024.
- 15 Dec 2021Received
- 15 Feb 2022Approved
- 23 Mar 2022Final approval
- 9 Feb 2024Building started
Planning details
- Status
- Building startedi
- Decision
- Approved with conditions · 15 Feb 2022
- Reference
- 21/872
- Received
- 15 Dec 2021
- Site
- 3,252 m²
What’s proposed
Construct a dwellinghouse and domestic garage, install a waste water treatment plant and undertake all associated site works
1 other application within 500 m in the last year
Open the reportNearby 1 · 500 m · 12 months
Distance
Time
Building started
- 9 Feb 2024 · Builder told the council work was starting (opted out of the finish sign-off) CN0109512LS
Protections nearby 250 m
- Recorded monument · 1
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
21/872 is a planning application to Cork County Council for construct a dwellinghouse and domestic garage, install a waste water treatment plant and, received on 15 Dec 2021; permission was granted with conditions on 15 Feb 2022.