Liskillea Waterfall Co. Cork
Approved in Apr 2022. No sign of building yet.
Start notices are matched from the national building control register; a start on site can be missed.
- 19 Jan 2022Received
- 15 Mar 2022Conditional
- 25 Apr 2022Final approval
- 25 Apr 2027Approval runs out
Planning details
- Status
- Approved
- Decision
- Conditional · 15 Mar 2022
- Reference
- 22/4068
- Received
- 19 Jan 2022
- Site
- 3.66 ha
What’s proposed
The Proposed development will consist of (A) an extension to the existing Bishopscourt Residential Care facility with the provision of 56 No. additional en-suite bedrooms, kitchen, dining facilities, staff facilities, offices, common areas, dayrooms, multipurpose social space, consultation rooms for visiting medical professionals, limited commercial retail support facilities, laundry, toilets, and other ancillary…
Show all
facilities linked to the existing residential care center; (B) The provision of 125 No. additional parking spaces, 58 No. bicycle parking spaces, internal roads and circulation routes, landscaping, boundary screen planting, and all associated site development works; (C) The removal of the existing treatment system and the provision of a new tertiary treatment wastewater system, provision of a secondary well and pump house, and mains water system within the site to serve the development; (D) Demolition of the existing kitchen, laundry facilities and plant room on the northern side of the existing building to facilitate the extension of the internal road network, the removal of the existing gas and water storage tanks and their relocation on site and making good on completion of the proposed development
2 other applications within 500 m in the last year
Open the reportNearby 2 · 500 m · 12 months
- Awaiting decisionBallynagrumoolia, Waterfall, Co. Cork.
- Appeal decidedLiskillea,, Waterfall, Co. Cork
Homes nearby
- For saleMeadowlands, Briar Hill, Near Cork, Waterfall, Co. Cork, T12 X2CA
- For saleGlendart, Ballinvoultig, Ballinvrinsig, Co. Cork, T12 KW5P
- For saleGoggins Hill, Ballinhassig, Co. Cork, T12 N205
- For saleGreybrook, Waterfall, Ballyburden, Co. Cork, T12 KWD6
- WithdrawnGogginshill, Ballinhassig, Co. Cork, T12 EYX2
- WithdrawnGreybrook, Waterfall, Co. Cork, T12 KWD6
Protections nearby 250 m
- Recorded monument · 4
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
22/4068 is a planning application to Cork County Council for the Proposed development will consist of (A) an extension to the existing Bishopscourt, received on 19 Jan 2022; permission was granted with conditions on 15 Mar 2022.