Approved in Sept 2022. Built and signed off.

  1. 19 Apr 2022Received
  2. 8 Aug 2022Conditional
  3. 30 Sept 2022Final approval
  4. 3 Mar 2023Building started
  5. 16 Oct 2024Signed off

Planning details

Status
Building started
Decision
Conditional · 8 Aug 2022
Reference
22/4884
Received
19 Apr 2022
Site
291 m²

What’s proposed

(1) Demolition of part of an existing dwelling and complete demolition of a shop, construction of a two storey semi-detached dwelling in it's place and all associated site work, (2) Modifications to existing dwelling house, consisting of the construction of 6 dormer windows, proposed changes to windows at the rear of the house, internal modifications and all associated site works

7 other applications within 500 m in the last year

Open the free report

Nearby 7 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Building started

  • 3 Mar 2023 · Builder told the council work was starting CN0098180CC

Protections nearby 250 m

  • NIAH-recorded building · 11
    house; boathouse
Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

22/4884 is a planning application to Cork County Council for (1) Demolition of part of an existing dwelling and complete demolition of a shop, received on 19 Apr 2022; permission was granted with conditions on 8 Aug 2022.