Dromalour Coolclogh Kanturk Co. Cork
Refused in Sept 2022.
- 12 Jul 2022Received
- 2 Sept 2022Refused
Earlier approval here ran out with no sign of building: 16/4601 (2017)
- Status
- Refused
- Decision
- Refused · 2 Sept 2022
- Council
- Cork County Council
- Type
- EXTENSION OF DURATION
- Site
- 12.23 ha
Live near Dromalour Coolclogh Kanturk Co. Cork?
Everything else planned on your street, in one report.
Check my streetWhat’s proposed
A 5 MW solar farm comprising approximately 22,200 photovoltaic panels on ground mounted frames within a site area of 12.23 hectares, 2 no. single storey inverter/transformer stations, 1 no. single storey delivery station, security fencing, CCTV and all associated ancillary development works - Extension of Duration to Permission granted under Planning Ref. No. 16/4601
Planning details
- Reference
- 22/5620
- Local authority
- Cork County Council
- Status
- Refused · register status “APPLICATION FINALISED”
- Received
- 12 Jul 2022
- Observations close
- 16 Aug 2022 (closed 1516 days ago)
- Decision due
- 5 Sept 2022 · decided 2 Sept 2022
- Decision
- Refused on 2 Sept 2022
- Proposed development
- A 5 MW solar farm comprising approximately 22,200 photovoltaic panels on ground mounted frames within a site area of 12.23 hectares, 2 no. single storey inverter/transformer stations, 1 no. single storey delivery station, security fencing, CCTV and all associated ancillary development works - Extension of Duration to Permission granted under Planning Ref. No. 16/4601As published by the register.
- Site area
- 12.23 ha from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Nearby 4 · 500 m · 5 years
Homes nearby
Zoning
Protected high-amenity landscape. Development is resisted to preserve the character of the area.
Protections nearby 250 m
No mapped flood area nearby.
- Recorded monument · 2
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 18 Sept 2026, 15:44 | open |
Summary