PlanningRegister.ie
Cork County Council · 22/5656

Kilnaglory Lisheens Greenfield Co.Cork

Approved in 2022. No sign of building yet.

  1. 15 Jul 2022Received
  2. 10 Nov 2022Conditional
  3. 13 Dec 2022Final approval
  4. 13 Dec 2032Approval runs out
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Approved
Decision
Conditional · 10 Nov 2022
Council
Cork County Council
Type
PERMISSION
Site
2.11 ha

Live near Kilnaglory Lisheens Greenfield Co.Cork?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

Intend to apply for 10 year planning permission. Underground electricity grid connection cabling, substation and ancillary site works. The development will comprise (1) a grid connection consisting of medium voltage cables and ducting in a excavated trench with a total length of c.1194 meters which will be installed on private land and public roads (L-2216 & L-22161); (2) control/switching substation consisting of either (i) single storey block building or (ii) 2 no. modular units; (3) cable beam over grange hill stream; (4) provision of ring main unit (RMU); (5) and all associated site development and reinstatement works. The proposed development includes minor revisions to the approved layout of the solar farm previously permitted under Cork County Council planning reference 18/5760 comprising omission of substation and satellite mast, and provision of the above referenced RMU, and the addition of a cable beam and underground cabling. The purpose of the proposed development is to connect the permitted solar farm under reference 18/5760 to the national grid at the existing Ballincollig 38Kv substation

Planning details

Reference
22/5656
Local authority
Cork County Council
Status
Granted with conditions · register status “APPLICATION FINALISED”
Received
15 Jul 2022
Observations close
19 Aug 2022 (closed 1508 days ago)
Decision due
14 Nov 2022 · decided 10 Nov 2022
Decision
Conditional on 10 Nov 2022
Proposed development
Intend to apply for 10 year planning permission. Underground electricity grid connection cabling, substation and ancillary site works. The development will comprise (1) a grid connection consisting of medium voltage cables and ducting in a excavated trench with a total length of c.1194 meters which will be installed on private land and public roads (L-2216 & L-22161); (2) control/switching substation consisting of either (i) single storey block building or (ii) 2 no. modular units; (3) cable beam over grange hill stream; (4) provision of ring main unit (RMU); (5) and all associated site development and reinstatement works. The proposed development includes minor revisions to the approved layout of the solar farm previously permitted under Cork County Council planning reference 18/5760 comprising omission of substation and satellite mast, and provision of the above referenced RMU, and the addition of a cable beam and underground cabling. The purpose of the proposed development is to connect the permitted solar farm under reference 18/5760 to the national grid at the existing Ballincollig 38Kv substation
As published by the register.
Site area
2.11 ha from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 1 · 500 m · 5 years

Explore this area on the map →

Homes nearby

Zoning

Not zoned in the current plan.

Protections nearby 250 m

No mapped flood area nearby.

  • Recorded monument · 6
    Quarry; Fulacht fia

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: npad · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
npadCC-BY-4.018 Sept 2026, 15:44open
Summary

22/5656 is a planning application to Cork County Council for intend to apply for 10 year planning permission. Underground electricity grid connection, received on 15 Jul 2022; permission was granted with conditions on 10 Nov 2022.