PlanningRegister.ie
Cork County Council · 22/5890

Currabeha Crookstown Co. Cork

Withdrawn.

  1. 16 Aug 2022Received
  2. 20 Sept 2022Observations closed

Earlier approval here ran out with no sign of building: 16/4783 (2017)

Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Withdrawn or invalid
Decision
Not yet
Council
Cork County Council
Type
EXTENSION OF DURATION
Site
8.62 ha

Live near Currabeha Crookstown Co. Cork?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

A 5 MW solar farm comprising approximately 22,200 photovoltaic panels on ground mounted frames within a site area of 8.5 hectares, 2 no. single storey inverter/transformer stations, 1 no. single storey delivery station, security fencing, CCTV and all associated ancillary development works Extension of Duration to Permission granted under Planning Ref. No. 16/4783

Planning details

Reference
22/5890
Local authority
Cork County Council
Status
Withdrawn or invalid · register status “WITHDRAWN”
Received
16 Aug 2022
Observations close
20 Sept 2022 (closed 1480 days ago)
Decision due
No due date published
Decision
Not decided
Proposed development
A 5 MW solar farm comprising approximately 22,200 photovoltaic panels on ground mounted frames within a site area of 8.5 hectares, 2 no. single storey inverter/transformer stations, 1 no. single storey delivery station, security fencing, CCTV and all associated ancillary development works Extension of Duration to Permission granted under Planning Ref. No. 16/4783
As published by the register.
Site area
8.62 ha from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby none · 500 m · 5 years

No other application within 500 m in the last 5 years.

Explore this area on the map →

Homes nearby

Zoning

Not zoned in the current plan.

Protections nearby 250 m

No mapped flood area nearby.

Nothing else protected nearby.

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: npad · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
npadCC-BY-4.018 Sept 2026, 15:44open
Summary

22/5890 is a planning application to Cork County Council for a 5 MW solar farm comprising approximately 22,200 photovoltaic panels on ground mounted, received on 16 Aug 2022; the file is recorded as withdrawn.