Cork County Council · 22/5896
Ballinvuskig West Mourneabbey Mallow Co. Cork
Approved in Nov 2022. Building started in 2023.
- 16 Aug 2022Received
- 10 Oct 2022Conditional
- 15 Nov 2022Final approval
- 10 Mar 2023Building started
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
- Status
- Building startedi
- Decision
- Conditional · 10 Oct 2022
- Council
- Cork County Council
- Type
- PERMISSION
- Site
- 3,404 m²
Live near Ballinvuskig West Mourneabbey Mallow…?
Everything else planned on your street, in one report.
Check my streetWhat’s proposed
Permission to construct a dwelling, Domestic garage and all associated site works
Planning details
- Reference
- 22/5896
- Local authority
- Cork County Council
- Status
- Commenced · register status “APPLICATION FINALISED”
- Received
- 16 Aug 2022
- Observations close
- 20 Sept 2022 (closed 1481 days ago)
- Decision due
- 10 Oct 2022 · decided 10 Oct 2022
- Decision
- Conditional on 10 Oct 2022
- Proposed development
- Permission to construct a dwelling, Domestic garage and all associated site worksAs published by the register.
- Site area
- 3,404 m² from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Nearby none · 500 m · 5 years
No other application within 500 m in the last 5 years.
Building started
- 10 Mar 2023 · Builder told the council work was starting (opted out of the finish sign-off) CN0098276CC
Zoning
Not zoned in the current plan.
Protections nearby 250 m
No mapped flood area nearby.
Nothing else protected nearby.
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 18 Sept 2026, 15:44 | open |
Summary
22/5896 is a planning application to Cork County Council for permission to construct a dwelling, Domestic garage and all associated site works, received on 16 Aug 2022; permission was granted with conditions on 10 Oct 2022.