Cork County Council · 23/4121
Meadstown Carrigaline Co. Cork
Approved in May 2023. Building started in 2024.
- 30 Jan 2023Received
- 27 Mar 2023Conditional
- 12 May 2023Final approval
- 15 Mar 2024Building started
Planning details
- Status
- Building startedi
- Decision
- Conditional · 27 Mar 2023
- Reference
- 23/4121
- Received
- 30 Jan 2023
- Site
- 4,981 m²
What’s proposed
Permission to construct a single dwelling, along with all the associated site works, including the installation of a wastewater treatment facility, the installation of a bored well for the supply of potable water and the creation of a new vehicular entrance onto the public road; along with the landscaping of the site
6 other applications within 500 m in five years
Open the reportNearby 6 · 500 m · 5 years
Distance
Time
Homes nearby
Building started
- 15 Mar 2024 · Builder told the council work was starting CN0110822CC
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
23/4121 is a planning application to Cork County Council for permission to construct a single dwelling, along with all the associated site works, received on 30 Jan 2023; permission was granted with conditions on 27 Mar 2023.