Bawnard East, Bawnard West, Garranekinnefeake, Jamesbrook, Kilva, Rathcoursey East, Scartlea Lower, Scartlea Upper, Co.Cork
- 22 Jun 2023Received
- 15 Aug 2023Refused
- Status
- Refused
- Decision
- Refused · 15 Aug 2023
- Council
- Cork County Council
- Type
- Permission
- Site
- 125.26 ha
What’s proposed
10 year planning permission for a solar farm with a total area of circa 126 hectares comprising of solar panels on ground mounted frames with a surface area of circa 532,000m2, 21 no. single storey electrical inverter/transformer stations, 5 no. single storey energy storage modules, 3 no. single storey spare parts containers, 12 no. ring main units, 5 no. weather stations, underground electrical ducting and cabling within the development site, private lands and within the R630, L7657, L7658 and L7659 public roads to connect to solar farm field parcels, security fencing, CCTV, access tracks, 1 no. drain deck crossing, temporary construction compounds, landscaping and all associated ancillary development works. Construction and operational access will be via entrances from L7657, L7658 and L7659. The operational life span of the solar farm will be 40 years and planning permission is requested for its duration. A Natura Impact Statement (NIS) has been prepared and submitted to the planning authority with the application
23/5270 is a planning application to Cork County Council for 10 year planning permission for a solar farm with a total area of circa 126 hectares, received on 22 Jun 2023; permission was refused on 15 Aug 2023.
Planning details
- Reference
- 23/5270
- Local authority
- Cork County Council
- Status
- Refused · register status “Application Closed”
- Received
- 22 Jun 2023
- Observations close
- 27 Jul 2023 (closed 1156 days ago)
- Decision due
- 15 Aug 2023 · decided 15 Aug 2023
- Decision
- Refused on 15 Aug 2023
- Proposed development
- 10 year planning permission for a solar farm with a total area of circa 126 hectares comprising of solar panels on ground mounted frames with a surface area of circa 532,000m2, 21 no. single storey electrical inverter/transformer stations, 5 no. single storey energy storage modules, 3 no. single storey spare parts containers, 12 no. ring main units, 5 no. weather stations, underground electrical ducting and cabling within the development site, private lands and within the R630, L7657, L7658 and L7659 public roads to connect to solar farm field parcels, security fencing, CCTV, access tracks, 1 no. drain deck crossing, temporary construction compounds, landscaping and all associated ancillary development works. Construction and operational access will be via entrances from L7657, L7658 and L7659. The operational life span of the solar farm will be 40 years and planning permission is requested for its duration. A Natura Impact Statement (NIS) has been prepared and submitted to the planning authority with the applicationAs published by the register.
- Site area
- 125.26 ha from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Nearby 2 applications within 500 m in the last 5 years
Appeal
Not appealed.
Commencement
No commencement notice matched to this reference.
Zoning at the site
No zoning objective covers this site in the current plan.
Designations within 250 m
No OPW flood extent nearby.
No other designation nearby.
Provenance
Register row from the national planning applications feed (NPAD), fetched 18 Sept 2026, 15:44 (store id 324357). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: https://planning.agileapplications.ie/corkcoco/application-details/?ref=23/5270.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 18 Sept 2026, 15:44 | open |