Cork County Council · 24/189
Foilnamuck Ballydehob Co. Cork
Approved in Jan 2025. Building started in 2025.
- 19 Apr 2024Received
- 29 Nov 2024Conditional
- 10 Jan 2025Final approval
- 21 Apr 2025Building started
Planning details
- Status
- Building startedi
- Decision
- Conditional · 29 Nov 2024
- Reference
- 24/189
- Received
- 19 Apr 2024
- Site
- 1,267 m²
What’s proposed
Construction of dwelling house, wastewater treatment system and all associated site development works. Permission is also sought to upgrade the wastewater system permitted under planning reference 962/98 serving the adjacent domestic property and revised site boundaries for same
2 other applications within 500 m in the last year
Open the reportNearby 2 · 500 m · 12 months
Distance
Time
- GrantedFoilnamuck Ballydehob Co. Cork P81 X953
- WithdrawnFoilnamuck Ballydehob Co. Cork P81 X953
- WithdrawnFoilnamuck Ballydehob Co. Cork
- RefusedFoilnamuck Ballydehob Co. Cork
- WithdrawnFoilnamuck Ballydehob Co. Cork P81 AY75
- CommencedFoilnamuck Ballydehob Co. Cork
- GrantedFoilnamuck Ballydehob Co. Cork
- CommencedFoilnamuck Ballydehob Co. Cork
- GrantedGlaisin Alainn Foilnamuck Ballydehob Co. Cork P81 TK28
- WithdrawnGlaisin Alainn Foilnamuck Ballydehob, Co. Cork P81TK28
- WithdrawnGlaisin Alainn Foilnamuck Ballydehob Co. Cork P81 TK28
- WithdrawnFoilnamuck Ballydehob Co. Cork
- GrantedThe Fortress Foilnamuck Ballydehob Co. Cork P81 RX23
- WithdrawnThe Fortress Foilnamuck Ballydehob Co. Cork, P81 RX23
- CommencedFoilnamuck Ballydehob Co. Cork
- GrantedFoilnamuck Ballydehob Co. Cork
Homes nearby
Building started
- 21 Apr 2025 · Builder told the council work was starting (opted out of the finish sign-off) CN0127325CC
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
24/189 is a planning application to Cork County Council for construction of dwelling house, wastewater treatment system and all associated site, received on 19 Apr 2024; permission was granted with conditions on 29 Nov 2024.