Wild Atlantic Glamping Ardagh Bere Island Co. Cork
Approved in Nov 2024. Building started in 2026.
- 9 Aug 2024Received
- 2 Oct 2024Conditional
- 5 Nov 2024Final approval
- 17 Sept 2026Building started
Earlier approval here ran out with no sign of building: 13/683 (2014)
- Status
- Building startedi
- Decision
- Conditional · 2 Oct 2024
- Council
- Cork County Council
- Type
- PERMISSION
- Site
- 1.56 ha
Live near Wild Atlantic Glamping Ardagh Bere…?
Everything else planned on your street, in one report.
Check my streetWhat’s proposed
(1) Retention of storage shed and modified site layout including 4nr. additional glamping tent pitches in lieu of 7 of the 14nr. previously permitted camping tent pitches. (2) Replacement of 6nr. existing glamping tent pitches with glamping pods, including associated site works for short term / holiday letting. All within the existing permitted capacity
Planning details
- Reference
- 24/437
- Local authority
- Cork County Council
- Status
- Commenced · register status “APPLICATION FINALISED”
- Received
- 9 Aug 2024
- Observations close
- 13 Sept 2024 (closed 761 days ago)
- Decision due
- 3 Oct 2024 · decided 2 Oct 2024
- Decision
- Conditional on 2 Oct 2024
- Site area
- 1.56 ha from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Nearby 6 · 500 m · 5 years
Building started
- 17 Sept 2026 · Builder told the council work was starting (opted out of the finish sign-off) CN0147411WW
Zoning
Not zoned in the current plan.
Protections nearby 250 m
No mapped flood area nearby.
- NIAH-recorded building · 1
- Recorded monument · 2
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 18 Sept 2026, 15:44 | open |
Summary
24/437 is a planning application to Cork County Council for (1) Retention of storage shed and modified site layout including 4nr. additional, received on 9 Aug 2024; permission was granted with conditions on 2 Oct 2024.