  1. 31 May 2024Received
  2. 5 Jul 2024Observations closed
  3. 25 Jul 2024Decision due
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Withdrawn or invalid
Decision
Due 25 Jul 2024
Council
Cork County Council
Type
PERMISSION
Site
3.76 ha

What’s proposed

Permission to construct a photovoltaic (Solar PV) energy generation scheme with a total area of 3.76ha within the townland of Ballybeg & Turbeagh, Co. Cork. The development will consist of the installation of 4,186 no. ground mounted Solar PV arrays, a 20kV substation, the installation of 120m of 20kV underground electrical cabling from the proposed substation to an existing pole and overhead line to connect to the national grid, the upgrade of an existing entrance off the local road to serve as a permanent site entrance for the solar farm and all associated site development works including upgrading 80m of existing tracks and installing 435m of new access track of 3m wide and all associated site works. The applicant is seeking a 10-year planning permission and an operational period of 40 Years

24/5008 is a planning application to Cork County Council for permission to construct a photovoltaic (Solar PV) energy generation scheme with a total, received on 31 May 2024; the file is recorded as incompleted application.

Planning details

Reference
24/5008
Local authority
Cork County Council
Status
Withdrawn or invalid · register status “INCOMPLETED APPLICATION”
Received
31 May 2024
Observations close
5 Jul 2024 (closed 813 days ago)
Decision due
25 Jul 2024
Decision
Not decided
Proposed development
Permission to construct a photovoltaic (Solar PV) energy generation scheme with a total area of 3.76ha within the townland of Ballybeg & Turbeagh, Co. Cork. The development will consist of the installation of 4,186 no. ground mounted Solar PV arrays, a 20kV substation, the installation of 120m of 20kV underground electrical cabling from the proposed substation to an existing pole and overhead line to connect to the national grid, the upgrade of an existing entrance off the local road to serve as a permanent site entrance for the solar farm and all associated site development works including upgrading 80m of existing tracks and installing 435m of new access track of 3m wide and all associated site works. The applicant is seeking a 10-year planning permission and an operational period of 40 Years
As published by the register.
Site area
3.76 ha from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 3 applications within 500 m in the last 5 years

Explore this area on the map →

Appeal

Not appealed.

Commencement

No commencement notice matched to this reference.

    Zoning at the site

    No zoning objective covers this site in the current plan.

    Designations within 250 m

    No OPW flood extent nearby.

    No other designation nearby.

    Provenance

    Register row from the national planning applications feed (NPAD), fetched 18 Sept 2026, 15:44 (store id 322216). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: https://planning.agileapplications.ie/corkcoco/application-details/?ref=24/5008.

    Source: npad · fetched 18 Sept 2026, 15:44
    SourceLicenceFetchedLink
    npadCC-BY-4.018 Sept 2026, 15:44open