Gneeves Millstreet Co.Cork
- 26 Nov 2024Received
- 9 Jan 2025Observations closed
- 29 Jan 2025Decision due
- Status
- Withdrawn or invalid
- Decision
- Due 29 Jan 2025
- Council
- Cork County Council
- Type
- PERMISSION
- Site
- 32.23 ha
What’s proposed
A fifteen (15) year planning permission for continuation of the operational life of the existing Gneeves wind farm from the date of expiration (November 2025) of the current planning permission (N/99/616, 03/6585, 04/188). The site measures 10.101 hectares. The existing wind farm consists of the following; 11 no. existing, operational Vestas V52 wind turbines, 8 no. turbines have a tip height of 91 m and a hub height of 65m, the remaining 3 no. turbines have a tip height of 76.1m and a hub height of 49m. All 11turbines have a rotor diameter of 52m. 1 no. existing operational onsite substation compound, the compound comprises: 38kV electrical substation, a control building, associated electrical plant and equipment, security fencing, associated underground cabling, existing site access tracks and 11 no. turbine hardstandings, existing operational site drainage infrastructure and associated works, including maintenance and improvement works. A Natura Impact Statement (NIS) and Environmental Impact Assessment Report (EIAR) have been prepared in relation to the project and accompany this planning application
24/6238 is a planning application to Cork County Council for a fifteen (15) year planning permission for continuation of the operational life of the, received on 26 Nov 2024; the file is recorded as incompleted application.
Planning details
- Reference
- 24/6238
- Local authority
- Cork County Council
- Status
- Withdrawn or invalid · register status “INCOMPLETED APPLICATION”
- Received
- 26 Nov 2024
- Observations close
- 9 Jan 2025 (closed 618 days ago)
- Decision due
- 29 Jan 2025
- Decision
- Not decided
- Proposed development
- A fifteen (15) year planning permission for continuation of the operational life of the existing Gneeves wind farm from the date of expiration (November 2025) of the current planning permission (N/99/616, 03/6585, 04/188). The site measures 10.101 hectares. The existing wind farm consists of the following; 11 no. existing, operational Vestas V52 wind turbines, 8 no. turbines have a tip height of 91 m and a hub height of 65m, the remaining 3 no. turbines have a tip height of 76.1m and a hub height of 49m. All 11turbines have a rotor diameter of 52m. 1 no. existing operational onsite substation compound, the compound comprises: 38kV electrical substation, a control building, associated electrical plant and equipment, security fencing, associated underground cabling, existing site access tracks and 11 no. turbine hardstandings, existing operational site drainage infrastructure and associated works, including maintenance and improvement works. A Natura Impact Statement (NIS) and Environmental Impact Assessment Report (EIAR) have been prepared in relation to the project and accompany this planning applicationAs published by the register.
- Site area
- 32.23 ha from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Nearby 1 application within 500 m in the last 5 years
Appeal
Not appealed.
Commencement
No commencement notice matched to this reference.
Zoning at the site
No zoning objective covers this site in the current plan.
Designations within 250 m
No OPW flood extent nearby.
No other designation nearby.
Provenance
Register row from the national planning applications feed (NPAD), fetched 18 Sept 2026, 15:44 (store id 324350). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: https://planning.agileapplications.ie/corkcoco/application-details/?ref=24/6238.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 18 Sept 2026, 15:44 | open |