Berrings Near Berrings Co. Cork
- 5 Dec 2024Received
- 3 Dec 2025Refused
- Status
- Refused
- Decision
- Refused · 3 Dec 2025
- Council
- Cork County Council
- Type
- Permission
- Site
- 21.24 ha
What’s proposed
The development will consist of: The development and operation of a c.13.8MW solar photovoltaic (PV) farm at a 21.25ha site located off the L2760. The application seeks a 10-year permission with an operational lifetime of 35 years and includes: • Approximately 37, 000 solar photovoltaic panels on ground mounted metal frames including string inverters mounted to the rear of the panels, with a maximum table height above ground of approximately 2.7 metres; • 1 no. 38kV substation including 1 no. MV switch room, 1 no. IPP control room, 1 no. ESB switch room and associated electrical infrastructure; • 3 no. transformer units; • Underground cabling and ducting; • 1 no. temporary construction compound and ancillary facilities for the duration of the construction phase of the project; • Perimeter fencing; • CCTV; • Construction and operational access provided from the existing site entrance off the L2760; • Internal tracks, site landscaping and all associated site enabling and site development works
24/6312 is a planning application to Cork County Council for the development will consist of: The development and operation of a c.13.8MW solar, received on 5 Dec 2024; permission was refused on 3 Dec 2025.
Planning details
- Reference
- 24/6312
- Local authority
- Cork County Council
- Status
- Refused · register status “Appeal decided ACP - Case Closed”
- Received
- 5 Dec 2024
- Observations close
- 20 Jan 2025 (closed 608 days ago)
- Decision due
- 3 Dec 2025 · decided 3 Dec 2025
- Decision
- Refused on 3 Dec 2025
- Proposed development
- The development will consist of: The development and operation of a c.13.8MW solar photovoltaic (PV) farm at a 21.25ha site located off the L2760. The application seeks a 10-year permission with an operational lifetime of 35 years and includes: • Approximately 37, 000 solar photovoltaic panels on ground mounted metal frames including string inverters mounted to the rear of the panels, with a maximum table height above ground of approximately 2.7 metres; • 1 no. 38kV substation including 1 no. MV switch room, 1 no. IPP control room, 1 no. ESB switch room and associated electrical infrastructure; • 3 no. transformer units; • Underground cabling and ducting; • 1 no. temporary construction compound and ancillary facilities for the duration of the construction phase of the project; • Perimeter fencing; • CCTV; • Construction and operational access provided from the existing site entrance off the L2760; • Internal tracks, site landscaping and all associated site enabling and site development worksAs published by the register.
- Site area
- 21.24 ha from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Nearby nothing else within 500 m in the last 5 years
No other application within 500 m in the last 5 years.
Appeal
Not appealed.
Commencement
No commencement notice matched to this reference.
Zoning at the site
No zoning objective covers this site in the current plan.
Designations within 250 m
No OPW flood extent nearby.
No other designation nearby.
Provenance
Register row from the national planning applications feed (NPAD), fetched 18 Sept 2026, 15:44 (store id 324379). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: https://planning.agileapplications.ie/corkcoco/application-details/?ref=24/6312.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 18 Sept 2026, 15:44 | open |