Site 1a Harbours Edge (formerly Belvery) Lower Aghada Co Cork

Approved in Mar 2025. Building started in 2025.

What’s proposed

Permission for the construction of the following: 1) A second site entrance to allow for full site wheelchair accessibility to the lower ground floor, 2) A new two storey detached dwelling with rooftop plantroom, 3) An open sided covered carport at lower ground floor level, 4) All associated site works

  1. 13 Dec 2024Received
  2. 13 Feb 2025Conditional
  3. 21 Mar 2025Final approval
  4. 9 Jun 2025Building started

Earlier approval here ran out with no sign of building: 21/5756 (2021)

Planning details

Status
Building startedi
Decision
Conditional · 13 Feb 2025
Reference
24/6399
Received
13 Dec 2024
Site
965 m²

1 other application within 500 m in the last year

Get the full report

Nearby 1 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Building started

  • 9 Jun 2025 · Builder told the council work was starting (opted out of the finish sign-off) CN0129564CC

Zoning

R2 — Existing residential

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

24/6399 is a planning application to Cork County Council for permission for the construction of the following: 1) A second site entrance to allow for, received on 13 Dec 2024; permission was granted with conditions on 13 Feb 2025.