PlanningRegister.ie
Cork County Council · 24/699

Bantry General Hospital Carrignagat Bantry Co. Cork

Approved in Mar 2025. No sign of building yet.

  1. 18 Dec 2024Received
  2. 19 Feb 2025Conditional
  3. 26 Mar 2025Final approval
  4. 26 Mar 2030Approval runs out

Earlier approval here ran out with no sign of building: 13/702 (2014)

Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Approved
Decision
Conditional · 19 Feb 2025
Council
Cork County Council
Type
PERMISSION
Site
3.51 ha

Live near Bantry General Hospital Carrignagat…?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

The construction of a two-storey building extension to the existing hospital to provide a 16-bed Rehabilitation Unit and Undercroft Plant Area at ground floor level, a 24 bed in-patient ward at first floor level and a Louvred Plant room Enclosure at roof level. Permission is also sought for refurbishment works within the ground floor of the existing hospital and the placement of a Plant room on the existing hospital roof. The works will include all associated site development works, realignment of existing parking spaces to provide additional parking, the upgrade of the adjoining landscaping and amenity areas associated with the proposed Stroke Rehabilitation Unit and In-Patient Ward building extension and permission for modifications to northern end of the existing pedestrian walkway which runs along the eastern boundary and associated ancillary works

Planning details

Reference
24/699
Local authority
Cork County Council
Status
Granted with conditions · register status “APPLICATION FINALISED”
Received
18 Dec 2024
Observations close
31 Jan 2025 (closed 615 days ago)
Decision due
20 Feb 2025 · decided 19 Feb 2025
Decision
Conditional on 19 Feb 2025
Proposed development
The construction of a two-storey building extension to the existing hospital to provide a 16-bed Rehabilitation Unit and Undercroft Plant Area at ground floor level, a 24 bed in-patient ward at first floor level and a Louvred Plant room Enclosure at roof level. Permission is also sought for refurbishment works within the ground floor of the existing hospital and the placement of a Plant room on the existing hospital roof. The works will include all associated site development works, realignment of existing parking spaces to provide additional parking, the upgrade of the adjoining landscaping and amenity areas associated with the proposed Stroke Rehabilitation Unit and In-Patient Ward building extension and permission for modifications to northern end of the existing pedestrian walkway which runs along the eastern boundary and associated ancillary works
As published by the register.
Site area
3.51 ha from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 62 · 500 m · 5 years

Show all 62

Explore this area on the map →

Homes nearby

Zoning

R2 — Existing residential

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

S2 — Sustainable neighbourhood infrastructure

Reserved for the schools, creches, community and health facilities a neighbourhood needs.

S5 — Sustainable neighbourhood infrastructure

Reserved for the schools, creches, community and health facilities a neighbourhood needs.

Protections nearby 250 m

No mapped flood area nearby.

  • NIAH-recorded building · 27
    G.W. Biggs and Company; house
  • Recorded monument · 2
    Burial ground; R106789

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: npad · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
npadCC-BY-4.018 Sept 2026, 15:44open
Summary

24/699 is a planning application to Cork County Council for the construction of a two-storey building extension to the existing hospital to provide, received on 18 Dec 2024; permission was granted with conditions on 19 Feb 2025.