Approved. Building started.

  1. 11 Jan 2024Received
  2. 15 Feb 2024Observations closed
  3. 6 Mar 2024Decision due
  4. 16 Jul 2025Building started
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Building started
Decision
Due 6 Mar 2024
Council
Cork County Council
Type
PERMISSION
Site
9,480 m²

Live near Kilnaclasha Skibbereen Co. Cork?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

Construction of a new glamping complex for use as short-term accommodation at lands located at Kilnaclasha, Skibbereen, Co. Cork. Proposed works will include: 1) removal of an existing derelict agricultural shed from site, to facilitate the proposed development; 2) Construction of 5 no. new glamping pods for use as short-term accommodation; 3) installation of new bin storage area; 4) construction of associated pathways and parking areas; 5) construction of new footway to tie in to an existing track to the north of the site, connecting the proposed glamping complex to the existing working farm; 6) all associated site development works. Access to the site will be provided via a shared existing site entrance and internal access track, currently serving existing short-term letting units

Planning details

Reference
24/8
Local authority
Cork County Council
Status
Commenced · register status “WITHDRAWN”
Received
11 Jan 2024
Observations close
15 Feb 2024 (closed 965 days ago)
Decision due
6 Mar 2024
Decision
Not decided
Proposed development
Construction of a new glamping complex for use as short-term accommodation at lands located at Kilnaclasha, Skibbereen, Co. Cork. Proposed works will include: 1) removal of an existing derelict agricultural shed from site, to facilitate the proposed development; 2) Construction of 5 no. new glamping pods for use as short-term accommodation; 3) installation of new bin storage area; 4) construction of associated pathways and parking areas; 5) construction of new footway to tie in to an existing track to the north of the site, connecting the proposed glamping complex to the existing working farm; 6) all associated site development works. Access to the site will be provided via a shared existing site entrance and internal access track, currently serving existing short-term letting units
As published by the register.
Site area
9,480 m² from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby none · 500 m · 5 years

No other application within 500 m in the last 5 years.

Explore this area on the map →

Homes nearby

Building started

  • 16 Jul 2025 · Builder told the council work was starting (opted out of the finish sign-off) CN0130895LM

Zoning

G3 — High amenity

Protected high-amenity landscape. Development is resisted to preserve the character of the area.

Protections nearby 250 m

No mapped flood area nearby.

Nothing else protected nearby.

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: npad · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
npadCC-BY-4.018 Sept 2026, 15:44open
Summary

24/8 is a planning application to Cork County Council for construction of a new glamping complex for use as short-term accommodation at lands, received on 11 Jan 2024; the file is recorded as withdrawn.