Brookville Ballyviniter Lower Mallow Co Cork
Approved in Oct 2025. Building started in 2025.
- 31 Jul 2025Received
- 19 Sept 2025Approved
- 24 Oct 2025Final approval
- 1 Dec 2025Building started
Planning details
- Status
- Building startedi
- Decision
- Approved with conditions · 19 Sept 2025
- Reference
- 25/5535
- Received
- 31 Jul 2025
- Site
- 1,038 m²
What’s proposed
1) Construction of a new single storey side extension. 2) Demolition of the existing garage to accommodate the new side extension. 3) Demolition and re-construction of the existing rear conservatory. 4) Elevational changes to the existing house. 5) Internal alterations to the existing layout. 6) All associated site works
18 other applications within 500 m in five years
Get the full reportNearby 18 · 500 m · 5 years
- RefusedClonmore Ballyviniter Lower Mallow Co.Cork
- Granted28 Clonmore Ballyviniter Lower, Ballyviniter Mallow Co.Cork
- WithdrawnClonmore Ballyviniter, Ballyviniter Lower Mallow Co.Cork
- Commenced9 Clonmore Ballyviniter Lower, Ballyviniter Mallow Co.Cork
- Withdrawn9 Clonmore Ballyviniter Mallow Co. Cork, P51D2NK
- Appeal decidedPolnareagha, Ardskeagh, Tullacondra, Croughta Kilmaclenine, Ballyclogh, Knockaunavaddreen, Copestown, Ballybeg, Baltydaniel East Twopothouse, Caurraghakerry, Co. Cork
- WithdrawnPolnareagha, Ardskeagh, Tullacondra, Croughta Kilmaclenine, Ballyclogh, Knockaunavaddreen, Copestown, Ballybeg, Baltydaniel East Twopothouse, Caurraghakerry, Co. Cork
- GrantedSpa Glen Mallow Co.Cork
Show all 18
- GrantedHazel Brooke Spaglen Mallow Co.Cork
- CommencedBallyvinter Lower Mallow Co. Cork
- Granted"Clonmore" Ballyviniter Lower Mallow Co.Cork
- GrantedBallyviniter Lower Mallow Co. Cork
- WithdrawnSpa Glen Mallow Co Cork
- GrantedHazel Brooke Spa Glen Mallow Co. Cork
- WithdrawnNo. 28 Clonmore Ballyviniter Lower Mallow Co. Cork
- WithdrawnHazel Brooke Parkadallane Co. Cork
- GrantedBallyviniter Lower Mallow Co. Cork
- GrantedNo. 134 Cairn Woods Ballyviniter Lower Mallow Co. Cork
Homes nearby
- For sale11 Brookfield, Ballyviniter, Mallow, Co. Cork, P51 R94X
- For saleRahan View, Spa Glen, Mallow, Co. Cork
- For saleRahan View, Spa Glen, Mallow, Co. Cork
- For sale18 Funshion, River Valley, Mallow, Co. Cork, P51 VYP3
- For sale11 Beechwood Park, Mallow, Co. Cork, P51 FC6H
- For sale17 Aldworth Heights, Saint Joseph'S Road, Mallow, Co. Cork, P51 VFR5
Building started
- 1 Dec 2025 · Builder told the council work was starting (opted out of the finish sign-off) CN0136082CC
Zoning
An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
25/5535 is a planning application to Cork County Council for 1) Construction of a new single storey side extension. 2) Demolition of the existing, received on 31 Jul 2025; permission was granted with conditions on 19 Sept 2025.