PlanningRegister.ie
Cork County Council · 26/1333

St. Mary's Secondary School, Mallow, Co. Cork, P51 PY04

Withdrawn or invalid.

  1. 19 May 2026Received
  2. 23 Jun 2026Observations closed

Earlier approval here ran out with no sign of building: 18/5473 (2019)

Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Withdrawn or invalid
Decision
Not yet
Council
Cork County Council
Type
Permission
Site
2.05 ha

Live near St. Mary's Secondary School?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

the following development consisting of (a) the construction of a 3 storey extension to existing post primary school, connected by new link covered walkway at first floor level. Total proposed development floor area is 2802 sqm, comprising of general classrooms, admin area, and supported education unit plus ancillary staff/student facilities with external student areas, access road, parking and drop off facilities. Development to include PV Panel installation at roof level, Heat Pump enclosure, LPG Tank enclosure. Overall site area is 2.06 Ha (b) removal of existing temporary classroom accommodation along with all related service, and reinstatement of staff car parking on vacated area , removal of temporary parking facilities to ballcourt area, 2 new accessible parking spaces (c) installation of 3 no. flag poles on concrete plinth to front of existing school to plus all associated site works

Planning details

Reference
26/1333
Local authority
Cork County Council
Status
Withdrawn or invalid · register status “Invalid - Prepare Letters”
Received
19 May 2026
Observations close
23 Jun 2026 (closed 103 days ago)
Decision due
No due date published
Decision
Not decided
Proposed development
the following development consisting of (a) the construction of a 3 storey extension to existing post primary school, connected by new link covered walkway at first floor level. Total proposed development floor area is 2802 sqm, comprising of general classrooms, admin area, and supported education unit plus ancillary staff/student facilities with external student areas, access road, parking and drop off facilities. Development to include PV Panel installation at roof level, Heat Pump enclosure, LPG Tank enclosure. Overall site area is 2.06 Ha (b) removal of existing temporary classroom accommodation along with all related service, and reinstatement of staff car parking on vacated area , removal of temporary parking facilities to ballcourt area, 2 new accessible parking spaces (c) installation of 3 no. flag poles on concrete plinth to front of existing school to plus all associated site works
As published by the register.
Site area
2.05 ha from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 25 · 500 m · 5 years

Show all 25

Explore this area on the map →

Homes nearby

Zoning

G3 — High amenity

Protected high-amenity landscape. Development is resisted to preserve the character of the area.

R2 — Existing residential

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

Protections nearby 250 m

No mapped flood area nearby.

  • NIAH-recorded building · 3
    Convent of Mercy; Saint Patrick's National School
  • Recorded monument · 4
    Kiln - lime; Standing stone

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: npad · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
npadCC-BY-4.018 Sept 2026, 15:44open
Summary

26/1333 is a planning application to Cork County Council for the following development consisting of (a) the construction of a 3 storey extension to, received on 19 May 2026; the file is recorded as invalid - prepare letters.