Units 8 & 9, The Dargan Building (Block 7B), Heuston South Quarter, St. Johns Road, Kilmainham, Dublin 8
Data updated 12 Sept 2026 · register lag up to 7 days · sources & freshness
3372/22 is a planning application for permission at Units 8 & 9, The Dargan Building (Block 7B), Heuston South Quarter, St. Johns Road, Kilmainham, Dublin 8, received by Dublin City Council on 25 Feb 2022 and first seen by Planning Register on 11 Sept 2026. The application describes: The proposed development consists of the amalgamation of 2 no. ground floor retail units (Units 8 & 9) and a change of use to office, together with all associated and ancillary internal and external alterations to provide a single office unit of 146.3 sqm. Internal alterations include the removal of an existing internal partition wall and the provision of a kitchenette and toilets (including accessible toilet) to serve the office unit. External alterations along the northern (front) elevation include the provision of a signage area above the existing entrance to Unit 8 and the replacement of an existing access door (Unit 9 access door) with glazing. The council granted permission on 14 Apr 2022. The five-week observation window closed on 1 Apr 2022. A commencement notice (CN0114051DC) was lodged on 26 Apr 2024, so works have started on site. The site is zoned null under the Dublin City Council development plan. Within 500 m there are 68 other decided applications in the last five years and 15 appeals.
Proposal
The proposed development consists of the amalgamation of 2 no. ground floor retail units (Units 8 & 9) and a change of use to office, together with all associated and ancillary internal and external alterations to provide a single office unit of 146.3 sqm. Internal alterations include the removal of an existing internal partition wall and the provision of a kitchenette and toilets (including accessible toilet) to serve the office unit. External alterations along the northern (front) elevation include the provision of a signage area above the existing entrance to Unit 8 and the replacement of an existing access door (Unit 9 access door) with glazing.
- Status
- Decision Notice Issued
- Decision
- Grant permission on 14 Apr 2022
- Final grant
- 27 May 2022
- Site (from polygon)
- 142 m²
- Location precision
- site (coords_polygon)
Timeline
- 25 Feb 2022New applicationObservation window closed 1 Apr 2022
- 14 Apr 2022DecisionAppeal window closed 12 May 2022

Full planning report for 53.34507, -6.29713
One document, every dataset, each section with its source and fetch time. Print it or download it as a PDF. It informs a planning search; it is not a statutory search.
1 Where this is — preview
1 Deadlines still open
Appeal
Not appealed.
Commencement
- Commencement notice CN0114051DC
Zoning at the site
Zone Z5 - DEV PLAN 2022-2028
Z5: City Centre: To consolidate and facilitate the development of the central area, and to identify, reinforce, strengthen and protect its civic design character and dignity.
The main town centre — retail, offices, civic uses, apartments.
Designations within 250 m
OPW flood extent nearby — flag only (licence); floodinfo.ie.
- NIAH-recorded building · 11
- Radon risk area · 1
- Recorded monument · 9
Provenance
Register row from the national planning applications feed (NPAD), fetched 11 Sept 2026, 18:51 (store id 69951). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here.
Source: npad · fetched 11 Sept 2026, 18:51
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 11 Sept 2026, 18:51 | open |