Side of 10, Bellvue Cottages, Old Finglas Road, (Junction with Glasnevin Downs),Glasnevin, Dublin, 11
Data updated 12 Sept 2026 · register lag up to 7 days · sources & freshness
3487/20 is a planning application for permission at Side of 10, Bellvue Cottages, Old Finglas Road, (Junction with Glasnevin Downs),Glasnevin, Dublin, 11, received by Dublin City Council on 2 Oct 2020 and first seen by Planning Register on 11 Sept 2026. The application describes: The development will consist of: Construction of new three bed detached dormer bungalow (dormer in west elevation) with mansard roof (upper floor in roof) and 6sqm solar panels, all to the side of existing bungalow (No. 10). Existing vehicle access onto Glasnevin Downs widened to 3.2m for off street parking. All to include new water connection and boundaries untouched with all other services connected to existing. The council granted permission on 24 Nov 2020. The five-week observation window closed on 6 Nov 2020. A commencement notice (CN0082062DC) was lodged on 8 Oct 2021, so works have started on site. The site is zoned null under the Dublin City Council development plan. The scheme is for 1 unit. Within 500 m there are 56 other decided applications in the last five years and 7 appeals.
Proposal
The development will consist of: Construction of new three bed detached dormer bungalow (dormer in west elevation) with mansard roof (upper floor in roof) and 6sqm solar panels, all to the side of existing bungalow (No. 10). Existing vehicle access onto Glasnevin Downs widened to 3.2m for off street parking. All to include new water connection and boundaries untouched with all other services connected to existing.
- Status
- Decision Notice Issued
- Decision
- Grant permission on 24 Nov 2020
- Final grant
- 11 Jan 2021
- Units
- 1
- Site (from polygon)
- 639 m²
- Location precision
- site (coords_polygon)
Timeline
- 2 Oct 2020New applicationObservation window closed 6 Nov 2020
- 24 Nov 2020DecisionAppeal window closed 22 Dec 2020

Full planning report for 53.37864, -6.28538
One document, every dataset, each section with its source and fetch time. Print it or download it as a PDF. It informs a planning search; it is not a statutory search.
1 Where this is — preview
1 Deadlines still open
Appeal
Not appealed.
Commencement
- Opt out commencement notice CN0082062DC
Zoning at the site
Zone Z1 - DEV PLAN 2022-2028
Z9: Amenity/Open Space Lands/Green Network: To preserve, provide and improve recreational amenity, open space and ecosystem services.
Land zoned to stay open — parks, playing fields, amenity corridors. Built development is very hard to justify, which also means the view is protected.
Z1: Sustainable Residential Neighbourhoods: To protect, provide and improve residential amenities.
An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.
Designations within 250 m
OPW flood extent nearby — flag only (licence); floodinfo.ie.
- NIAH-recorded building · 1
- Radon risk area · 3
- Recorded monument · 3
Provenance
Register row from the national planning applications feed (NPAD), fetched 11 Sept 2026, 18:51 (store id 84303). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here.
Source: npad · fetched 11 Sept 2026, 18:51
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 11 Sept 2026, 18:51 | open |