Ballymun Civic Centre, Main Street, Ballymun, Dublin 9
Approved in Jan 2025. Building started in 2025.
What’s proposed
The development will consist of: Change of Use of existing Office areas on 1st & 2nd floors to Healthcare Facility use as part of reconfiguration & expansion of existing Healthcare Facility on Ground, 1st & 2nd floors of Ballymun Civic Centre, including internal alterations to enclose existing open plan office areas on 1st & 2nd floors (currently open to the internal atrium) with glazed screen enclosures, and minor alterations to the external façade on Main Street to incorporate ventilation grilles within the existing glazed curtain wall at first floor level
- 8 May 2024Received
- 10 Dec 2024Approved
- 31 Jan 2025Final approval
- 20 Aug 2025Building started
Planning details
- Status
- Building startedi
- Decision
- Approved · 10 Dec 2024
- Reference
- 3649/24
- Received
- 8 May 2024
- Further information
- Requested 2 Jul 2024 · received 15 Nov 2024
- Site
- 1,132 m²
9 other applications within 500 m in the last year
Get the full reportNearby 9 · 500 m · 12 months
- Awaiting decision15, Shangan Green, Ballymun, Dublin 9
- Awaiting decision7, Shanard Avenue, Dublin 9, D09 E627
- Withdrawn7, Shanard Avenue, Dublin 9, D09 E627
- Withdrawn15, Shangan Green, Ballymun, Dublin 9, D09 R3P3
- Granted54, Oldtown Avenue, Santry, Dublin 9, D09TK71
- CommencedUnits 1--7 Ground Floor, College View, Ballymun Road and Silloge Road, Ballymun, Dublin 11, D11 P8KF
- WithdrawnUnits 1--7 Ground Floor, College View, Ballymun Road and Silloge Road, Ballymun, Dublin 11, D11 P8KF
- GrantedThe Rediscovery Centre, Coultry Road, Ballymun, Dublin 9, D09HK58
- CommencedAspen Student Accommodation, Ballymun Road, Balbutcher Lane , Dublin 11, D11ETF7
- Granted91 Shanard Rd, White Hall, Dublin 9, D09 X6Y3
- Withdrawn91, Shanard Road, Dublin 9
- Granted23, Coultry Close, Ballumun , Dublin 9
- GrantedLands at Shangan Road, Ballymun, Dublin 9
- WithdrawnLands at Shangan Road, Ballymun, Dublin 9
- GrantedRediscovery Centre, Coultry Road, Ballymun, Dublin 9
- WithdrawnCoultry Road, Ballymun, Dublin 9, D09 HK58
- Refused94 Silloge Gardens, Ballymun, Dublin 11, D11 N2P1
- Withdrawn93, Silloge Gardens, Dublin 11
- GrantedCentra, Unit 1 , Shangan Hall , Shangan Road, Ballymun, Dublin 9
- GrantedCentra Off-licence, Unit 3, Shangan Hall, Shangan Road, Ballymun, Dublin 9
- CommencedUnit 3, Shangan Neighbourhood Centre, Shangan Road, Ballymun, Dublin 9, D09 E527
- CommencedScoil An Tseachtar Laoch National School, Ballymun Road, Dublin 11
- Appeal decided39, Shangan Crescent, Ballymun, Dublin 9, D09H2P4
- Withdrawn39 Shangan Crescent, Ballymun, Dublin 9
- GrantedSetanta GAA Club, 123, Ballymun Road, Dublin 11
- WithdrawnSetanta GAA Club, 123 Ballymun Road, Dublin 11
- Commenced155 Shanliss Road, Santry, Dublin 9, D09 P9E8
- Commenced17, Ard Na Meala, Ballymun, Dublin 11 D11 VP26
- Granted22, Oldtown Avenue, Santry, Dublin 9
- Appeal decided236, Ballymun Road, Dublin 9, D09 XP60
- GrantedRetail Unit No. 2, Aspen Building, Balcurris Road/Main Street, Ballymun, Dublin 11
- Granted39, Shangan Crescent, Ballymun, Dublin 9, D09 H2P4
- Withdrawn39, Shangan Crescent, Ballymun, Dublin 9
Homes nearby
- For saleApartment 31, Block C, The Gateway Student Village, Ballymun, Dublin 9, D09 VW42
- For saleApartment 76, Block E, The Gateway Student Village, Ballymun, Dublin 9, D09 KN32
- For saleApartment 101, College View, Ballymun, Dublin 11, D11 VY33
- For saleApartment 68 Collegeview, Silloge Road, Ballymun, Co. Dublin, D11 FC91
- For saleApartment 45, Block D, The Gateway Student Village, Ballymun, Dublin 9, D09 P6K0
- For sale6 Gateway Court, Ballymun, Dublin 11
Development land nearby
- Permitted, not started · 457 homes granted 24 Jul 2025, expires 24 Jul 2030 — North West corner of Omni Park Shopping Centre (1.0 km)
- Stalled build · 198 homes; commenced 23 May 2022, no completion certificate, planned end Dec 2023 — Northwood Avenue, Dublin (1.0 km)
- Public land off Gateway Student Village, Ballymun, Dublin 9 (0.1 km)
- Mixed-use land off Shangan Hall, Shangan Road (0.1 km)
- Public land off The Plaza, Ballymun, Dublin 9 (0.2 km)
Building started
- 20 Aug 2025 · Builder told the council work was starting CN0132292DC
Zoning
Zone Z4 - DEV PLAN 2022-2028
A local centre: shops, services and apartments over them, serving the surrounding housing.
Protections nearby 250 m
- Recorded monument · 1
Where this comes from
National planning feed (NPAD), fetched 11 Sept 2026, 18:51.
Source: National Planning Application Database · fetched 11 Sept 2026, 18:51
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 11 Sept 2026, 18:51 | open |
Summary
3649/24 is a planning application to Dublin City Council for the development will consist of: Change of Use of existing Office areas on 1st & 2nd, received on 8 May 2024; permission was granted on 10 Dec 2024.