29 Glasnevin Woods, Dublin 11

Approved in Jul 2022. Building started in 2022.

  1. 7 Apr 2022Received
  2. 1 Jun 2022Approved
  3. 15 Jul 2022Final approval
  4. 15 Aug 2022Building started

Planning details

Status
Building startedi
Decision
Approved · 1 Jun 2022
Reference
3687/22
Received
7 Apr 2022
Site
299 m²

What’s proposed

Planning Permission to construct dormer window in attic storage area on rear elevation of roof with flat roof finish

4 other applications within 500 m in the last year

Open the report

Nearby 4 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Development land nearby

See all development land near here →

Building started

  • 15 Aug 2022 · Builder told the council small works were starting CN0092445DC

Zoning

Zone Z1 - DEV PLAN 2022-2028

R2 — Existing residential

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

Protections nearby 250 m

Flood area nearby (OPW maps). floodinfo.ie ↗

  • NIAH-recorded building · 2
    Tolka Lodge; Ardstraw House
  • Recorded monument · 5
    Mill - unclassified; Bridge
Where this comes from

National planning feed (NPAD), fetched 11 Sept 2026, 18:51.

Source: National Planning Application Database · fetched 11 Sept 2026, 18:51
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.011 Sept 2026, 18:51open
Summary

3687/22 is a planning application to Dublin City Council for planning Permission to construct dormer window in attic storage area on rear elevation, received on 7 Apr 2022; permission was granted on 1 Jun 2022.