Dublin City Council · 3866/20

Site at Milltown Park, Sandford Road, Dublin 6

  1. 4 Dec 2020Received
  2. 7 Sept 2021Grant permission
  3. 4 Oct 2021Appealed
  4. 10 Feb 2023Appeal: Granted with conditions
  5. 10 Feb 2023Final grant
  6. 21 Jul 2023Commenced
Status
Commenced
Decision
Grant permission · 7 Sept 2021
Council
Dublin City Council
Type
Permission
Site
671 m²
Appeal
ACP 311552 · Granted with conditions

What’s proposed

Permission for development at a 0.054 Ha site at Milltown Park, Sandford Road, Dublin 6. The development will principally consist of the demolition of 83.7 sq m of the 'red brick link building' (single storey over basement) which forms part of the Jesuit Community Buildings and the construction of a new 2.4 metre high boundary wall across the site from east to west. The proposed works to the red brick link building include the following: - the demolition of a 3 no. bay section of facade and a section of roof; - the removal of a section of the internal floor area and provision of new internal stairs; - the removal of the existing 'means of escape' external stairs from the roof; - the construction of a new gable wall and parapet over roof to match existing, - a new external 'means of escape' stairs from roof level and a new security fence to the 'means of escape' stairs. The development will also consist of hard and soft landscaping and all other associated site works (internally and externally) above and below ground

3866/20 is a planning application to Dublin City Council for permission for development at a 0.054 Ha site at Milltown Park, Sandford Road, Dublin 6., received on 4 Dec 2020; permission was granted on 7 Sept 2021.

Planning details

Reference
3866/20
Local authority
Dublin City Council
Status
Commenced · register status “Appeal Decided”
Received
4 Dec 2020
Observations close
18 Jan 2021 (closed 2082 days ago)
Decision due
9 Sept 2021 · decided 7 Sept 2021
Decision
Grant permission on 7 Sept 2021
Proposed development
Permission for development at a 0.054 Ha site at Milltown Park, Sandford Road, Dublin 6. The development will principally consist of the demolition of 83.7 sq m of the 'red brick link building' (single storey over basement) which forms part of the Jesuit Community Buildings and the construction of a new 2.4 metre high boundary wall across the site from east to west. The proposed works to the red brick link building include the following: - the demolition of a 3 no. bay section of facade and a section of roof; - the removal of a section of the internal floor area and provision of new internal stairs; - the removal of the existing 'means of escape' external stairs from the roof; - the construction of a new gable wall and parapet over roof to match existing, - a new external 'means of escape' stairs from roof level and a new security fence to the 'means of escape' stairs. The development will also consist of hard and soft landscaping and all other associated site works (internally and externally) above and below ground
As published by the register.
Site area
671 m² from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name

Nearby 155 applications within 500 m in the last 5 years

Show all 155

Explore this area on the map →

Homes nearby

Development land nearby

From Buildable, our sister site for development land in Dublin.

See all development land near here →

Appeal

ACP 311552 · Planning Appeal · decided · Granted with conditions 10 Feb 2023
received by the Commission 4 Oct 2021 · inspector's report · board order

Commencement

  • Commencement notice CN0103301DC
    21 Jul 2023Sandford Road, Milltown, Dublin 6,, Dublin 6, D06 W9Y7matched by ref_exact

Zoning at the site

Zone Z12 - DEV PLAN 2022-2028

R2 — Existing residential

Z12: Institutional Land (Future Development Potential): To ensure existing environmental amenities are protected in the predominantly residential future use of these lands.

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

S5 — Sustainable neighbourhood infrastructure

Z15: Community and Social Infrastructure: To protect and provide for community uses and social infrastructure.

Reserved for the schools, creches, community and health facilities a neighbourhood needs.

Designations within 250 m

No OPW flood extent nearby.

  • Radon risk area · 1
    About 1 in 20 homes in this area is likely to have high radon levels
  • Recorded monument · 2
    House - 18th/19th century; R187625

Provenance

Register row from the national planning applications feed (NPAD), fetched 11 Sept 2026, 18:51 (store id 84390). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here.

Source: npad · fetched 11 Sept 2026, 18:51
SourceLicenceFetchedLink
npadCC-BY-4.011 Sept 2026, 18:51open