Connolly Headquarters, Connolly Station, Amiens Street, Dublin 1, D01RW09
Data updated 13 Sept 2026 · register lag up to 7 days · sources & freshness
4365/23 is a planning application for permission at Connolly Headquarters, Connolly Station, Amiens Street, Dublin 1, D01RW09, received by Dublin City Council on 25 Aug 2023 and first seen by Planning Register on 11 Sept 2026. The application describes: PROTECTED STRUCTURE: permission for the deep energy retrofit of its 'Annexe' wing offices at Connolly Headquarters, Connolly Station, Amiens Street, Dublin 1 which is a protected structure. The works will include reconfiguration of the internal office space and the addition of appropriate insulation to the historic fabric along with supporting mechanical and electrical works. A new external staircase/lift structure will also be provided. The council granted permission on 27 Jun 2024. The five-week observation window closed on 29 Sept 2023. A commencement notice (SN0011371DC) was lodged on 15 Oct 2024, so works have started on site. The site is zoned null under the Dublin City Council development plan. Within 500 m there are 140 other decided applications in the last five years and 19 appeals.
Proposal
PROTECTED STRUCTURE: permission for the deep energy retrofit of its 'Annexe' wing offices at Connolly Headquarters, Connolly Station, Amiens Street, Dublin 1 which is a protected structure. The works will include reconfiguration of the internal office space and the addition of appropriate insulation to the historic fabric along with supporting mechanical and electrical works. A new external staircase/lift structure will also be provided.
- Status
- Decision Notice Issued
- Decision
- Grant permission on 27 Jun 2024
- Final grant
- 7 Aug 2024
- Site (from polygon)
- 402 m²
- Location precision
- site (coords_polygon)
Timeline
- 25 Aug 2023New applicationObservation window closed 29 Sept 2023
- 15 Feb 2024Further information requested
- 31 May 2024Further information received
- 27 Jun 2024DecisionAppeal window closed 25 Jul 2024

Full planning report for 53.35218, -6.24842
One document, every dataset, each section with its source and fetch time. Print it or download it as a PDF. It informs a planning search; it is not a statutory search.
1 Where this is — preview
1 Deadlines still open
Appeal
Not appealed.
Commencement
- Seven day notice SN0011371DC
Zoning at the site
Zone Z5 - DEV PLAN 2022-2028
Z5: City Centre: To consolidate and facilitate the development of the central area, and to identify, reinforce, strengthen and protect its civic design character and dignity.
The main town centre — retail, offices, civic uses, apartments.
Designations within 250 m
OPW flood extent nearby — flag only (licence); floodinfo.ie.
- NIAH-recorded building · 93
- Radon risk area · 1
- Recorded monument · 2
Provenance
Register row from the national planning applications feed (NPAD), fetched 11 Sept 2026, 18:51 (store id 80024). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here.
Source: npad · fetched 11 Sept 2026, 18:51
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 11 Sept 2026, 18:51 | open |