The Conrad Hotel, Earlsfort Terrace, Dublin 2, D02 V562
Data updated 12 Sept 2026 · register lag up to 7 days · sources & freshness
WEB1010/26 is a planning application for permission at The Conrad Hotel, Earlsfort Terrace, Dublin 2, D02 V562, received by Dublin City Council on 5 Jan 2026 and first seen by Planning Register on 11 Sept 2026. The application describes: We, Earlsfort Centre Hotel Proprietors Limited, intend to apply for planning permission for development at The Conrad Hotel, Earlsfort Terrace, Dublin 2, D02 V562. To the north of the site, is the St. Stephen’s Green House office complex. A portion of the application site also fronts onto Leeson Street Lower. To the south of the site is the Earlsfort Centre office complex, and to the east of the site are the offices fronting onto Lesson Street Lower including Ormonde House, with the National Concert Hall opposite, to the west. The proposed development comprises upgrades works and extension of the existing hotel, including: • Elevational upgrade works to the existing hotel including replacement and enhancement of windows; • A new 8 storey extension over existing event space, resulting in a 10 storey building with accommodation and reconfiguration of the existing event space at ground level with additional head height and ancillary spaces at first floor and 8 No floors of bedroom accommodation; • Internal modifications and improvements to hotel facilities; • 7th floor extension to Earlsfort Terrace and provision of additional floor to existing hotel providing resulting in a 9 no. storey building with set back to Earlsfort Terrace over existing basement and lower ground floor; • Existing bar and restaurant facade upgrade facing Earlsfort Plaza; • An increase in hotel bedrooms from 192 No. to 308 No. (an increase of 6,189 sqm); and • All associated works, site development, landscaping, plant, demolition and construction work and consequential revisions to the existing hotel internally and externally. The planning application may be inspected or purchased at a fee not exceeding the reasonable cost of making a copy, at the offices of Dublin City Council, Planning Department, Block 4, Ground Floor, Civic Offices, Wood Quay, Dublin 8 during its public opening hours (9.00a.m.- 4.30p.m.). A submission or observation in relation to the application may be made in writing to the planning authority on payment of the prescribed fee (€20.00) within the period of 5 weeks beginning on the date of receipt by the authority of the application, and such submissions or observations will be considered by the planning authority in making a decision on the application. The planning authority may grant permission subject to or without conditions, or may refuse to grant permission. The council granted permission on 17 Apr 2026. The five-week observation window closed on 9 Feb 2026. The site is zoned null under the Dublin City Council development plan. Within 500 m there are 130 other decided applications in the last five years and 37 appeals.
Proposal
We, Earlsfort Centre Hotel Proprietors Limited, intend to apply for planning permission for development at The Conrad Hotel, Earlsfort Terrace, Dublin 2, D02 V562. To the north of the site, is the St. Stephen’s Green House office complex. A portion of the application site also fronts onto Leeson Street Lower. To the south of the site is the Earlsfort Centre office complex, and to the east of the site are the offices fronting onto Lesson Street Lower including Ormonde House, with the National Concert Hall opposite, to the west. The proposed development comprises upgrades works and extension of the existing hotel, including: • Elevational upgrade works to the existing hotel including replacement and enhancement of windows; • A new 8 storey extension over existing event space, resulting in a 10 storey building with accommodation and reconfiguration of the existing event space at ground level with additional head height and ancillary spaces at first floor and 8 No floors of bedroom accommodation; • Internal modifications and improvements to hotel facilities; • 7th floor extension to Earlsfort Terrace and provision of additional floor to existing hotel providing resulting in a 9 no. storey building with set back to Earlsfort Terrace over existing basement and lower ground floor; • Existing bar and restaurant facade upgrade facing Earlsfort Plaza; • An increase in hotel bedrooms from 192 No. to 308 No. (an increase of 6,189 sqm); and • All associated works, site development, landscaping, plant, demolition and construction work and consequential revisions to the existing hotel internally and externally. The planning application may be inspected or purchased at a fee not exceeding the reasonable cost of making a copy, at the offices of Dublin City Council, Planning Department, Block 4, Ground Floor, Civic Offices, Wood Quay, Dublin 8 during its public opening hours (9.00a.m.- 4.30p.m.). A submission or observation in relation to the application may be made in writing to the planning authority on payment of the prescribed fee (€20.00) within the period of 5 weeks beginning on the date of receipt by the authority of the application, and such submissions or observations will be considered by the planning authority in making a decision on the application. The planning authority may grant permission subject to or without conditions, or may refuse to grant permission.
- Status
- Decision Notice Issued
- Decision
- Grant permission on 17 Apr 2026
- Final grant
- 26 May 2026
- Site (from polygon)
- 4,707 m²
- Location precision
- site (coords_polygon)
Timeline
- 5 Jan 2026New applicationObservation window closed 9 Feb 2026
- 25 Feb 2026Further information requested
- 25 Mar 2026Further information received
- 17 Apr 2026DecisionAppeal window closed 15 May 2026

Full planning report for 53.33491, -6.25732
One document, every dataset, each section with its source and fetch time. Print it or download it as a PDF. It informs a planning search; it is not a statutory search.
1 Where this is — preview
1 Deadlines still open
Appeal
Not appealed.
Commencement
No commencement notice matched to this reference.
Zoning at the site
Zone Z8 - DEV PLAN 2022-2028
Z6: Employment/Enterprise: To provide for the creation and protection of enterprise and facilitate opportunities for employment creation.
Zoned for employment uses. Housing is not the intended use here.
Z8: Georgian Conservation Areas: To protect the existing architectural and civic design character, and to allow only for limited expansion consistent with the conservation objective.
Zoned to protect the open land between urban areas. Development is strongly resisted.
Designations within 250 m
No OPW flood extent nearby.
- NIAH-recorded building · 198
- Radon risk area · 1
- Recorded monument · 10
Provenance
Register row from the national planning applications feed (NPAD), fetched 11 Sept 2026, 18:51 (store id 87862). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here.
Source: npad · fetched 11 Sept 2026, 18:51
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 11 Sept 2026, 18:51 | open |