PlanningRegister.ie
Dublin City Council · WEB1062/19

8 Cedarwood Park, Glasnevin, Dublin 11

Approved in May 2019. Building started in 2019.

  1. 11 Feb 2019Received
  2. 5 Apr 2019Approved
  3. 10 May 2019Final approval
  4. 18 Sept 2019Building started
Status
Building startedi
Decision
Approved · 5 Apr 2019
Council
Dublin City Council
Type
Permission
Site
348 m²

Live near 8 Cedarwood Park?

Everything else planned on your street, in one report.

Check my street

What’s proposed

The development will consist of a ground floor extension to the rear and side and the demolition of the existing garage

Planning details

Reference
WEB1062/19
Local authority
Dublin City Council
Status
Commenced · register status “Decision Notice Issued”
Received
11 Feb 2019
Observations close
19 Mar 2019 (closed 2766 days ago)
Decision due
5 Apr 2019 · decided 5 Apr 2019
Decision
Grant permission on 5 Apr 2019
Site area
348 m² from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name

Nearby 86 · 500 m · 5 years

Show all 86

Explore this area on the map →

Homes nearby

Development land nearby

From Buildable, our sister site for development land in Dublin.

See all development land near here →

Building started

  • 18 Sept 2019 · Builder told the council work was starting (opted out of the finish sign-off) CN0056636DC

Zoning

Zone Z1 - DEV PLAN 2022-2028

R2 — Existing residential

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

Protections nearby 250 m

No mapped flood area nearby.

Nothing else protected nearby.

Where this comes from

National planning feed (NPAD), fetched 11 Sept 2026, 18:51.

Source: npad · fetched 11 Sept 2026, 18:51
SourceLicenceFetchedLink
npadCC-BY-4.011 Sept 2026, 18:51open
Summary

WEB1062/19 is a planning application to Dublin City Council for the development will consist of a ground floor extension to the rear and side and the, received on 11 Feb 2019; permission was granted on 5 Apr 2019.