Site of c. 4.4609 ha located within the school campus at Alexandra College, Richmond Avenue South, Milltown, Dublin 6, D06 KX50.
- 3 Mar 2026Received
- 24 Apr 2026Grant permission
- 2 Jun 2026Final grant
- 6 Jul 2026Commenced
- Status
- Commenced
- Decision
- Grant permission · 24 Apr 2026
- Council
- Dublin City Council
- Type
- Permission
- Site
- 6.44 ha
What’s proposed
The proposed development will consist of the demolition of the existing single storey Music Building and associated glass link corridor connection to the Senior School (c. 295 sq.m) and the construction of a new 1–4 storey Science, Technology, Engineering, Arts and Maths (STEAM) building (c. 3048 sq.m) inclusive of the provision of the following elements throughout: Reception, 2 no. art rooms, atrium/ collaborative space, town hall space, 3 no. store rooms, plant room, toilets and changing space at ground floor level. Collaboration space, 2 no. science labs, computer lab, art room, town hall space, preparation room, 2 no. store rooms, recording studio, lobby and toilets at first floor level. 2 no. science labs, 5 no. maths rooms, preparation room and toilets at second floor level. Collaboration space, 2 no. science labs, preparation room and toilets at third floor level. The proposal includes the provision of stair cores, lifts and circulation spaces throughout the STEAM building. The proposed development will include the provision of all associated signage and lighting, provision of plant and PV panels at roof level and associated roof access point for servicing/ maintenance only, blue/ green roofs, hard and soft landscaping and boundary treatments, attenuation proposals, all associated infrastructural and site development works above and below ground and associated connections to services (foul and surface water drainage and water supply) and the provision of an ESB substation (c.28 sq.m) at one of the indicative locations shown, subject to agreement with ESB
WEB1482/26 is a planning application to Dublin City Council for the proposed development will consist of the demolition of the existing single storey, received on 3 Mar 2026; permission was granted on 24 Apr 2026.
Planning details
- Reference
- WEB1482/26
- Local authority
- Dublin City Council
- Status
- Commenced · register status “Decision Notice Issued”
- Received
- 3 Mar 2026
- Observations close
- 7 Apr 2026 (closed 161 days ago)
- Decision due
- 27 Apr 2026 · decided 24 Apr 2026
- Decision
- Grant permission on 24 Apr 2026
- Proposed development
- The proposed development will consist of the demolition of the existing single storey Music Building and associated glass link corridor connection to the Senior School (c. 295 sq.m) and the construction of a new 1–4 storey Science, Technology, Engineering, Arts and Maths (STEAM) building (c. 3048 sq.m) inclusive of the provision of the following elements throughout: Reception, 2 no. art rooms, atrium/ collaborative space, town hall space, 3 no. store rooms, plant room, toilets and changing space at ground floor level. Collaboration space, 2 no. science labs, computer lab, art room, town hall space, preparation room, 2 no. store rooms, recording studio, lobby and toilets at first floor level. 2 no. science labs, 5 no. maths rooms, preparation room and toilets at second floor level. Collaboration space, 2 no. science labs, preparation room and toilets at third floor level. The proposal includes the provision of stair cores, lifts and circulation spaces throughout the STEAM building. The proposed development will include the provision of all associated signage and lighting, provision of plant and PV panels at roof level and associated roof access point for servicing/ maintenance only, blue/ green roofs, hard and soft landscaping and boundary treatments, attenuation proposals, all associated infrastructural and site development works above and below ground and associated connections to services (foul and surface water drainage and water supply) and the provision of an ESB substation (c.28 sq.m) at one of the indicative locations shown, subject to agreement with ESBAs published by the register.
- Site area
- 6.44 ha from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name
Full planning report for 53.31097, -6.25043
Zoning, appeals, sold prices, flood and heritage constraints — everything for this area in one PDF.
No account, no payment. Not a statutory planning search.
Appeal
Not appealed.
Commencement
- Commencement notice CN0144420DC
Zoning at the site
Zone Z1 - DEV PLAN 2022-2028
Z1: Sustainable Residential Neighbourhoods: To protect, provide and improve residential amenities.
An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.
Z15: Community and Social Infrastructure: To protect and provide for community uses and social infrastructure.
Reserved for the schools, creches, community and health facilities a neighbourhood needs.
Designations within 250 m
OPW flood extent nearby — flag only (licence); floodinfo.ie.
- Radon risk area · 2
- Record of Protected Structures · 2
- Recorded monument · 11
Provenance
Register row from the national planning applications feed (NPAD), fetched 11 Sept 2026, 18:51 (store id 88449). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here.
Source: npad · fetched 11 Sept 2026, 18:51
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 11 Sept 2026, 18:51 | open |