PlanningRegister.ie
Dublin City Council · WEB2095/22

21 Mask Road, Artane, Dublin 5 D05 C9Y

Approved in Jun 2023. Building started in 2024.

  1. 6 Dec 2022Received
  2. 28 Apr 2023Approved
  3. 9 Jun 2023Final approval
  4. 30 Jul 2024Building started
Status
Building startedi
Decision
Approved · 28 Apr 2023
Council
Dublin City Council
Type
Permission
Site
204 m²

What’s proposed

The development consists of planning to create a vehicular access all to the front of the existing house, exiting onto Mask Road, Artane, Dublin 5 and for a single storey porch to the front and for a single storey extension to the side and rear of existing house and for all associated site works

Planning details

Reference
WEB2095/22
Local authority
Dublin City Council
Status
Commenced · register status “Decision Notice Issued”
Received
6 Dec 2022
Decision due
28 Apr 2023 · decided 28 Apr 2023
Decision
Grant permission on 28 Apr 2023
Site area
204 m² from the mapped boundary, not the council's figure

Live near 21 Mask Road?

Everything else planned on your street, in one report.

Check my street
Council register ↗

Nearby 30 · 500 m · 12 months

Distance
Time
Show all 30

Explore this area on the map →

Homes nearby

Development land nearby

See all development land near here →

Building started

  • 30 Jul 2024 · Builder told the council small works were starting CN0117714DC

Zoning

Zone Z1 - DEV PLAN 2022-2028

R2 — Existing residential

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

Protections nearby 250 m

  • NIAH-recorded building · 2
    Church of Our Lady of Mercy; post box

Where this comes from

National planning feed (NPAD), fetched 11 Sept 2026, 18:51.

Source: National Planning Application Database · fetched 11 Sept 2026, 18:51
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.011 Sept 2026, 18:51open
Summary

WEB2095/22 is a planning application to Dublin City Council for the development consists of planning to create a vehicular access all to the front of, received on 6 Dec 2022; permission was granted on 28 Apr 2023.