AIB Bank, 7/12 Dame Street, Dublin 2
Data updated 12 Sept 2026 · register lag up to 7 days · sources & freshness
WEB2443/25 is a planning application for permission at AIB Bank, 7/12 Dame Street, Dublin 2, received by Dublin City Council on 19 Jun 2025 and first seen by Planning Register on 11 Sept 2026. The application describes: PROTECTED STRUCTURE: We, Allied Irish Bank PLC, intend to apply for permission for remedial works to a Recorded Protected Structure (RPS Ref. No.2099 under the Dublin City Development Plan 2022-2028) at this site: AIB, 7-12 Dame Street, Dublin 2, Co. Dublin. The application relates to: (i) Internal alteration works to accommodate new protected lobbies to existing stairs and fire upgrades to existing screens and doors, removal of non-original walls, upgrade of existing ground floor mezzanine to 60-minute fire rating and formation of new fire escape opening in original fabric. (ii) Fire safety upgrade works to fire detection & alarm, lighting and small power to the Basement Floor, Ground Floor, Ground Mezzanine Floor, First Floor, First Mezzanine Floor, Second Floor, and Third Floor. (iii) External alteration works to the Dame Lane Elevation to accommodate a new fire escape exit door. The council granted permission on 13 Aug 2025. The five-week observation window closed on 24 Jul 2025. A commencement notice (CN0134117DC) was lodged on 6 Oct 2025, so works have started on site. The site is zoned null under the Dublin City Council development plan. Within 500 m there are 134 other decided applications in the last five years and 52 appeals.
Proposal
PROTECTED STRUCTURE: We, Allied Irish Bank PLC, intend to apply for permission for remedial works to a Recorded Protected Structure (RPS Ref. No.2099 under the Dublin City Development Plan 2022-2028) at this site: AIB, 7-12 Dame Street, Dublin 2, Co. Dublin. The application relates to: (i) Internal alteration works to accommodate new protected lobbies to existing stairs and fire upgrades to existing screens and doors, removal of non-original walls, upgrade of existing ground floor mezzanine to 60-minute fire rating and formation of new fire escape opening in original fabric. (ii) Fire safety upgrade works to fire detection & alarm, lighting and small power to the Basement Floor, Ground Floor, Ground Mezzanine Floor, First Floor, First Mezzanine Floor, Second Floor, and Third Floor. (iii) External alteration works to the Dame Lane Elevation to accommodate a new fire escape exit door.
- Status
- Decision Notice Issued
- Decision
- Grant permission on 13 Aug 2025
- Final grant
- 17 Sept 2025
- Site (from polygon)
- 848 m²
- Location precision
- site (coords_polygon)
Timeline
- 19 Jun 2025New applicationObservation window closed 24 Jul 2025
- 13 Aug 2025DecisionAppeal window closed 10 Sept 2025

Full planning report for 53.34399, -6.26578
One document, every dataset, each section with its source and fetch time. Print it or download it as a PDF. It informs a planning search; it is not a statutory search.
1 Where this is — preview
1 Deadlines still open
Appeal
Not appealed.
Commencement
- Short commencement notice CN0134117DC
Zoning at the site
Zone Z5 - DEV PLAN 2022-2028
Z5: City Centre: To consolidate and facilitate the development of the central area, and to identify, reinforce, strengthen and protect its civic design character and dignity.
The main town centre — retail, offices, civic uses, apartments.
Designations within 250 m
OPW flood extent nearby — flag only (licence); floodinfo.ie.
- NIAH-recorded building · 296
- Radon risk area · 2
- Recorded monument · 110
Provenance
Register row from the national planning applications feed (NPAD), fetched 11 Sept 2026, 18:51 (store id 84541). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here.
Source: npad · fetched 11 Sept 2026, 18:51
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 11 Sept 2026, 18:51 | open |