Site known as The Carriageworks, which forms part of the former Castleforbes Business Park, Sheriff Street Upper and East Road, Dublin 1
Data updated 12 Sept 2026 · register lag up to 7 days · sources & freshness
WEB5913/25 is a planning application for permission at Site known as The Carriageworks, which forms part of the former Castleforbes Business Park, Sheriff Street Upper and East Road, Dublin 1, received by Dublin City Council on 9 Dec 2025 and first seen by Planning Register on 11 Sept 2026. The application describes: The site is bound by Sheriff St Upper to the south, the railway yards to the north, the completed Freight Building and Premier Inn to the east, and East Road to the west. The proposed development consists of minor amendments to the permitted and under construction development, as permitted under ABP-308827-20 (DCC Ref: SHD0026/20) and as amended under 3782/24 and WEB2583/25. The proposed amendments relate to the permitted standalone childcare facility, the ground floor of Block C2 and associated landscaping and not relating to any residential units. The proposed amendments include: 1. Relocation of the permitted childcare facility from a standalone 2 storey building, located between Blocks C2 and Block C3 to the ground floor of Block C2. This involves the subdivision of the permitted 1 no. retail/cafe/restaurant unit in Block C2 (c.469 sq.m) into 2 no. units to include a change of use to a childcare facility of c.347.4 sq.m and a retail/café unit of c.117.7 sq.m. An external play area of c.100 sq.m at ground floor is provided to north of Block C2 adjoining the childcare facility. Minor amendments are proposed to the ground floor façade of Block C2 to amend access points and fire doors in line with the proposed subdivision. 2. Replacement of previously permitted standalone childcare facility with 1 no. covered padel court (10.3m x20m) with canopy roof (max height of c.8m, perimeter wall, lighting and amendment of site landscaping in this area to include for internal boundary fences, seating, relocated bike parking and level changes. The council granted permission on 31 Mar 2026. The five-week observation window closed on 22 Jan 2026. A commencement notice (SN0014184DC) was lodged on 22 May 2026, so works have started on site. The site is zoned null under the Dublin City Council development plan. Within 500 m there are 148 other decided applications in the last five years and 13 appeals.
Proposal
The site is bound by Sheriff St Upper to the south, the railway yards to the north, the completed Freight Building and Premier Inn to the east, and East Road to the west. The proposed development consists of minor amendments to the permitted and under construction development, as permitted under ABP-308827-20 (DCC Ref: SHD0026/20) and as amended under 3782/24 and WEB2583/25. The proposed amendments relate to the permitted standalone childcare facility, the ground floor of Block C2 and associated landscaping and not relating to any residential units. The proposed amendments include: 1. Relocation of the permitted childcare facility from a standalone 2 storey building, located between Blocks C2 and Block C3 to the ground floor of Block C2. This involves the subdivision of the permitted 1 no. retail/cafe/restaurant unit in Block C2 (c.469 sq.m) into 2 no. units to include a change of use to a childcare facility of c.347.4 sq.m and a retail/café unit of c.117.7 sq.m. An external play area of c.100 sq.m at ground floor is provided to north of Block C2 adjoining the childcare facility. Minor amendments are proposed to the ground floor façade of Block C2 to amend access points and fire doors in line with the proposed subdivision. 2. Replacement of previously permitted standalone childcare facility with 1 no. covered padel court (10.3m x20m) with canopy roof (max height of c.8m, perimeter wall, lighting and amendment of site landscaping in this area to include for internal boundary fences, seating, relocated bike parking and level changes.
- Status
- Decision Notice Issued
- Decision
- Grant permission on 31 Mar 2026
- Final grant
- 6 May 2026
- Site (from polygon)
- 1,771 m²
- Location precision
- site (coords_polygon)
Timeline
- 9 Dec 2025New applicationObservation window closed 22 Jan 2026
- 12 Feb 2026Further information requested
- 4 Mar 2026Further information received
- 31 Mar 2026DecisionAppeal window closed 28 Apr 2026

Full planning report for 53.35094, -6.23240
One document, every dataset, each section with its source and fetch time. Print it or download it as a PDF. It informs a planning search; it is not a statutory search.
1 Where this is — preview
1 Deadlines still open
Appeal
Not appealed.
Commencement
- Seven day notice SN0014184DC
Zoning at the site
Zone Z14 - DEV PLAN 2022-2028
Z14: Strategic Development and Regeneration Areas (SDRAs): To seek the social, economic and physical development and/or regeneration of an area with mixed-use, of which residential would be the predominant use.
A small rural settlement where only modest infill serving local need is envisaged.
Designations within 250 m
No OPW flood extent nearby.
- EPA-licensed facility · 2
- Radon risk area · 1
Provenance
Register row from the national planning applications feed (NPAD), fetched 11 Sept 2026, 18:51 (store id 86563). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here.
Source: npad · fetched 11 Sept 2026, 18:51
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 11 Sept 2026, 18:51 | open |