Clay Farm
Approved in May 2023. Building started in 2023; part signed off as finished in Sep 2023.
A newer start notice was filed in Feb 2024: a sign-off can cover one phase of the work.
What’s proposed
Viscount Securities intend to apply for planning permission for a Large-scale…
Cut short by the council feed. Full text ↗
This is Clay Farm. Read the scheme page →
- 17 Feb 2023Building started
- 27 Feb 2023Received
- 19 Apr 2023Approved
- 25 May 2023Final approval
- 5 Sept 2023Signed off
Planning details
- Status
- Building started
- Decision
- Approved · 19 Apr 2023
- Reference
- LRD23A/0126
- Type
- Permission (LRD)
- Received
- 27 Feb 2023
- Site
- 20.59 ha
6 other applications within 500 m in the last year
Get the full reportNearby 6 · 500 m · 12 months
- Awaiting decisionLands at and between, Carrickmines 220kV Substation, Ballyogan Road, Dublin 18, D18 X0D0 and,, Blackrock Park, Blackrock Park, Rock Road, Blackrock, Dublin.A94HWF6
- Withdrawn21 Clay Farm Glade, Dublin 18, D18 C3HW
- Granted21 Clay Farm Glade, Kilgobbin, Dublin 18, D18C3HW
- GrantedESB's Carrickmines 220KV Substation, Ballyogan Road, Carrickmines, Dublin 18
- Commenced19, Cruagh Green, Stepaside, Dublin 18. D18XN63
- Granted18 Meadow Court, Stepaside Park, Stepaside, Dublin, D18 V9Y0
- Granted171, Stepaside Park, Kilgobbin, Stepaside, Dublin 18, D18Y9Y9
- Granted12 Clay Farm Grove, Kilgobbin, Dublin 18, D18Y3XP
- Withdrawn171, Stepaside Park, Kilgobbin, Stepaside, Dublin, D18Y9Y9
- Commenced14 Clay Farm Glade, Clay Farm, Ballyogan Road, Dublin 18, D18V5WD
- CommencedUnit 1, Clay Farm Drive, Clay Farm, Dublin 18
- Commenced170, Stepaside Park, Kilgobbin, Dublin 18, D18E6H6
- Withdrawn170, Stepaside Park, Kilgobbin, Dublin 18, D18E6H6
- Granted17 Clay Farm Grove, Clay Farm, Leopardstown, Dublin 18, D18X97E
- Withdrawn17, Clay Farm Grove, Leopardstown, Dublin 18, D18X97E
- Refused17 Clay Farm Grove, Leopardstown, Dublin 18, D18 X97E
- Commenced184, Stepaside Park, Stepaside, Dublin 18
- Appeal decidedSite at Clay Farm House (a protected structure), Killgobbin Road, Dublin 18, and at Clay Farm (Phase 2), Ballyogan Road, Dublin 18
- GrantedCirca 0.1ha site at Carrickmines 220kV substation, Jamestown, Ballyogan Road, Carrickmines, Dublin 18
- GrantedCarrickmines 220 KV Substation, Ballyogan Road, Carrickmines, Dublin 18
- Appeal decided1, Cruagh Close, Stepaside, Dublin 18, D18KW92
- Granted10, Cruagh Rise, Stepaside, Dublin 18, D18TW54
- Refused1, Cruagh Close, Dublin 18, D18KW92
- Refused2, Larkfield Place,Clay Farm, Ballyogan, Dublin 18, D18XE02
- WithdrawnSite at Clay Farm (Phase 2), Ballyogan Road, Dublin 18
- Refusedsite of c. 1.97 ha of the Clay Farm Loop Road linking with Clay Farm Phase 2 development, situated to the north-east of the existing Stepaside Park housing development, located in townland of Kilgobbin, Stepaside, Dublin 18
- Granted114 Stepaside Park, Jamestown, Dublin 18
- CommencedNo. 2 Larkfield Place, Clay Farm, Ballyogan, Co. Dublin (D18 XE02)
Homes nearby
- For sale18 Clay Farm Grove, Leopardstown, Dublin 18, D18 R92K
- For sale10 Clay Farm Green, Dublin 18, D18 VX0X
- For sale32 Meadow View, Clay Farm Place, Leopardstown, Dublin 18, D18 KX8E
- For sale22 Oak Hall, Larkfield View, Leopardstown, Dublin 18, D18 KXV1
- For saleApartment 38, The Cedar, Cruagh Wood, Stepaside, Dublin 18, D18 YK65
- For sale12 Cruagh Court, Stepaside, Co. Dublin, D18 N127
Development land nearby
- Permitted, not started · 57 homes granted 23 Jul 2025, expires 23 Jul 2030 — Leopardstown Village Centre Site B (0.7 km)
- Permitted, not started · 23 homes granted 21 Oct 2026, expires 21 Oct 2031 — Hill View (0.8 km)
- Permitted, not started · 120 homes granted 30 Oct 2026, expires 30 Oct 2031 — Riverside Cottage (0.9 km)
- Residential land off Clay Farm Court, Clay Farm (0.1 km)
- Residential land off Clay Farm Park, Clay Farm (0.1 km)
Building started
- 7 Feb 2024 · Builder told the council work was starting CN0109608DR
- 29 Sept 2023 · Builder told the council work was starting CN0105841DR
- 25 May 2023 · Builder told the council work was starting CN0101035DR
- 17 Feb 2023 · Builder told the council work was starting (seven-day notice) SN0008120DR
Zoning
Open space with active recreational amenities — pitches, courts, play areas.
An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.
An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.
Protections nearby 250 m
Flood area nearby (OPW maps). floodinfo.ie ↗
- EPA-licensed facility · 2
- NIAH-recorded building · 1
- Record of Protected Structures · 1
- Recorded monument · 10
Where this comes from
National planning feed (NPAD), fetched 10 Nov 2026, 23:01.
Source: National Planning Application Database · fetched 10 Nov 2026, 23:01
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 10 Nov 2026, 23:01 | open |
Summary
LRD23A/0126 is a planning application to Dún Laoghaire-Rathdown County Council for viscount Securities intend to apply for planning permission for a Large-scale Re, received on 27 Feb 2023; permission was granted on 19 Apr 2023.