PlanningRegister.ie
Donegal County Council · 1751218

Aghangaddy Glebe, Ramelton, Letterkenny PO

Approved in Oct 2017. Building started in 2018.

  1. 28 Jul 2017Received
  2. 14 Sept 2017Conditional
  3. 18 Oct 2017Final approval
  4. 18 Jan 2018Building started
Status
Building startedi
Decision
Conditional · 14 Sept 2017
Council
Donegal County Council
Type
PERMISSION
Units
1
Site
3,547 m²

Live near Aghangaddy Glebe?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

CONSTRUCTION OF A NEW DWELLING, DOMESTIC GARAGE AND WASTE WATER TREATMENT SYSTEM

Planning details

Reference
1751218
Local authority
Donegal County Council
Status
Commenced · register status “APPLICATION FINALISED”
Received
28 Jul 2017
Observations close
1 Sept 2017 (closed 3337 days ago)
Decision due
21 Sept 2017 · decided 14 Sept 2017
Decision
Conditional on 14 Sept 2017
Site area
3,547 m² from the mapped boundary, not the council's figure

Nearby 11 · 500 m · 5 years

Show all 11

Explore this area on the map →

Homes nearby

Building started

  • 18 Jan 2018 · Builder told the council work was starting (opted out of the finish sign-off) CN0036371DL

Not held yet for Donegal County Council: zoning.

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

1751218 is a planning application to Donegal County Council for construction of a new dwelling, domestic garage and waste water treatment system, received on 28 Jul 2017; permission was granted with conditions on 14 Sept 2017.