Donegal County Council · 1851426
DERRYDRUEL, UPPER MAGHERY, LETTERKENNY PO
Approved in 2018. Building started in 2022.
- 14 Sept 2018Received
- 26 Oct 2018Conditional
- 5 Dec 2018Final approval
- 12 Jul 2022Building started
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
- Status
- Building startedi
- Decision
- Conditional · 26 Oct 2018
- Council
- Donegal County Council
- Type
- PERMISSION
- Units
- 1
- Site
- 5,686 m²
What’s proposed
ERECTION OF A DWELLING WITH PROPRIETARY WASTEWATER TREATMENT SYSTEM INCLUDING ALL ASSOCIATED SITE WORKS
Planning details
- Reference
- 1851426
- Local authority
- Donegal County Council
- Status
- Commenced · register status “APPLICATION FINALISED”
- Received
- 14 Sept 2018
- Observations close
- 19 Oct 2018 (closed 2911 days ago)
- Decision due
- 8 Nov 2018 · decided 26 Oct 2018
- Decision
- Conditional on 26 Oct 2018
- Proposed development
- ERECTION OF A DWELLING WITH PROPRIETARY WASTEWATER TREATMENT SYSTEM INCLUDING ALL ASSOCIATED SITE WORKSAs published by the register.
- Site area
- 5,686 m² from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Nearby none · 500 m · 5 years
No other application within 500 m in the last 5 years.
Homes nearby
Building started
- 12 Jul 2022 · Builder told the council work was starting (opted out of the finish sign-off) CN0091236DL
Zoning
Not zoned in the current plan.
Protections nearby 250 m
No mapped flood area nearby.
Nothing else protected nearby.
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 18 Sept 2026, 15:44 | open |
Summary
1851426 is a planning application to Donegal County Council for erection of a dwelling with proprietary wastewater treatment system including all, received on 14 Sept 2018; permission was granted with conditions on 26 Oct 2018.