Donegal County Council · 1851562
Cashel, Ballyshannon, Donegal PO
Approved in Jan 2019. Building started in 2019.
- 10 Oct 2018Received
- 30 Nov 2018Conditional
- 16 Jan 2019Final approval
- 22 Mar 2019Building started
- Status
- Building startedi
- Decision
- Conditional · 30 Nov 2018
- Council
- Donegal County Council
- Type
- PERMISSION
- Site
- 1,450 m²
What’s proposed
DEMOLITION OF AN EXISTING SHED AND ERECTION OF NEW EXTENSIONS TO EXISTING DWELLING HOUSE INCLUDING AN ATTACHED GARAGE AND ALL ASSOCIATED SITE DEVELOPMENT WORKS
Planning details
- Reference
- 1851562
- Local authority
- Donegal County Council
- Status
- Commenced · register status “APPLICATION FINALISED”
- Received
- 10 Oct 2018
- Observations close
- 14 Nov 2018 (closed 2893 days ago)
- Decision due
- 4 Dec 2018 · decided 30 Nov 2018
- Decision
- Conditional on 30 Nov 2018
- Site area
- 1,450 m² from the mapped boundary, not the council's figure
Nearby 2 · 500 m · 5 years
Homes nearby
- For sale4 Kilbarron, Ballyshannon, Coolmore, Co. Donegal, F94 E363
- For saleThe Gaslight, Cool More, Coolmore, Co. Donegal, F94 X022
- For saleArdeelan Lower, Rossnowlagh, Bundoran, Co. Donegal, F94 C5P0
- For saleStation House, Ardeelan Lower, Rossnowlagh, Co. Donegal, F94 P6P2
- WithdrawnCool Beg, Rossnowlagh, Coolmore, Co. Donegal, F94 D5X2
- WithdrawnKilbarron, Ballyshannon, Coolmore, Co. Donegal, F94 DE0C
Building started
- 22 Mar 2019 · Builder told the council work was starting (opted out of the finish sign-off) CN0049516DL
Not held yet for Donegal County Council: zoning.
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
1851562 is a planning application to Donegal County Council for demolition of an existing shed and erection of new extensions to existing dwelling house, received on 10 Oct 2018; permission was granted with conditions on 30 Nov 2018.