PlanningRegister.ie
Donegal County Council · 2051035

Carricknamoghill, Killybegs, Donegal PO

Approved in Sept 2020.

  1. 29 Jul 2020Received
  2. 10 Sept 2020Unconditional
  3. 3 Aug 2025Approval runs out
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Approved
Decision
Unconditional · 10 Sept 2020
Council
Donegal County Council
Type
EXTENSION OF DURATION
Site
2,503 m²

Live near Carricknamoghill?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

ERECTION OF A SINGLE ELECTRICITY GENERATING WIND TURBINE (V39 500KW) WITH A HUB HEIGHT OF 50M AND ROTOR DIAMETER UP TO 40M, ASSOCIATED HARDSTANDING, ACCESS ROAD, DRAINAGE AND SITE WORKS TO BE LOCATED TO THE REAR OF ISLAND SEAFOODS LTD

Planning details

Reference
2051035
Local authority
Donegal County Council
Status
Granted · register status “APPLICATION FINALISED”
Received
29 Jul 2020
Observations close
2 Sept 2020 (closed 2229 days ago)
Decision due
22 Sept 2020 · decided 10 Sept 2020
Decision
Unconditional on 10 Sept 2020
Proposed development
ERECTION OF A SINGLE ELECTRICITY GENERATING WIND TURBINE (V39 500KW) WITH A HUB HEIGHT OF 50M AND ROTOR DIAMETER UP TO 40M, ASSOCIATED HARDSTANDING, ACCESS ROAD, DRAINAGE AND SITE WORKS TO BE LOCATED TO THE REAR OF ISLAND SEAFOODS LTD
As published by the register.
Site area
2,503 m² from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 1 · 500 m · 5 years

Explore this area on the map →

Homes nearby

Zoning

Not zoned in the current plan.

Protections nearby 250 m

No mapped flood area nearby.

Nothing else protected nearby.

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: npad · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
npadCC-BY-4.018 Sept 2026, 15:44open
Summary

2051035 is a planning application to Donegal County Council for erection of a single electricity generating wind turbine (v39 500kw) with a hub height, received on 29 Jul 2020; permission was granted on 10 Sept 2020.