  1. 9 Mar 2021Received
  2. 12 May 2022Conditional
  3. 4 Sept 2026Building started
Status
Building startedi
Decision
Conditional · 12 May 2022
Council
Donegal County Council
Type
PERMISSION
Site
5,548 m²

Live near Milk Isle?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

(1) ERECTION OF A WASTE TRANSFER STATION CONTAINED WITHIN THE EXISTING BUILDING (1,856 M2) HAVING AN ANNUAL WASTE INTAKE OF UP TO 24,500 TONNES/YEAR, (2) CONSTRUCTION OF A CIVIC AMENITY BRING CENTRE (408 M2) TO THE EAST OF THE EXISTING BUILDING AND ALL ASSOCIATED SITE WORKS AND SERVICES TO ACCOMMODATE THE CIVIC AMENITY SITE AND WASTE TRANSFER STATION AND (3) ALL ASSOCIATED SITE WORKS AND SERVICES, FOOTPATHS, UPGRADING OF SITE ACCESS AND BOUNDARY FENCE, BICYCLE PARKING RACKS, ADDITIONAL CAR PARKING SPACES AND LANDSCAPING

Planning details

Reference
2150424
Local authority
Donegal County Council
Status
Commenced · register status “APPLICATION FINALISED”
Received
9 Mar 2021
Observations close
13 Apr 2021 (closed 2016 days ago)
Decision due
19 May 2022 · decided 12 May 2022
Decision
Conditional on 12 May 2022
Site area
5,548 m² from the mapped boundary, not the council's figure

Nearby 8 · 500 m · 5 years

Explore this area on the map →

Homes nearby

Appeal

Appeal ABP-313721-22 (status unknown), not yet matched.

Building started

  • 4 Sept 2026 · Builder told the council work was starting (seven-day notice) SN0014778DL

Not held yet for Donegal County Council: zoning.

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

2150424 is a planning application to Donegal County Council for (1) erection of a waste transfer station contained within the existing building (1,856, received on 9 Mar 2021; permission was granted with conditions on 12 May 2022.