PlanningRegister.ie
Donegal County Council · 2152390

Garshooney, Killea, Lifford PO

Approved in May 2022. Building started in 2022.

  1. 30 Nov 2021Received
  2. 14 Apr 2022Conditional
  3. 19 May 2022Final approval
  4. 17 Aug 2022Building started
Status
Building startedi
Decision
Conditional · 14 Apr 2022
Council
Donegal County Council
Type
PERMISSION
Units
1
Site
2,706 m²

What’s proposed

CONSTRUCTION OF A DETACHED 1 1/2 STOREY DWELLING, DETACHED GARAGE; NEW VEHICULAR ENTRANCE, A NEW WASTEWATER TREATMENT PLANT WITH PERCOLATION AREA ALONG WITH CONNECTION TO EXISTING SERVICES

Planning details

Reference
2152390
Local authority
Donegal County Council
Status
Commenced · register status “APPLICATION FINALISED”
Received
30 Nov 2021
Decision due
18 Apr 2022 · decided 14 Apr 2022
Decision
Conditional on 14 Apr 2022
Site area
2,706 m² from the mapped boundary, not the council's figure

Live near Garshooney?

Everything else planned on your street, in one report.

Check my street
Council register ↗

Nearby 4 · 500 m · 5 years

Distance
Time

Explore this area on the map →

Building started

  • 17 Aug 2022 · Builder told the council work was starting (opted out of the finish sign-off) CN0092614DL

Not held yet for Donegal County Council: zoning.

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

2152390 is a planning application to Donegal County Council for construction of a detached 1 1/2 storey dwelling, detached garage; new vehicular, received on 30 Nov 2021; permission was granted with conditions on 14 Apr 2022.