Approved in Feb 2023. Building started in 2023, signed off as finished in Feb 2024.

What’s proposed

MODIFICATIONS TO THE GROUND FLOOR LAYOUT AND SHOP FACADE TO INCLUDE THE FOLLOWING: (1) SINGLE STOREY EXTENSION TO FRONT OF EXISTING STORE TO PROVIDE A DRS FACILITY TO ALLOW CUSTOMERS TO RETURN PLASTIC BEVERAGE BOTTLES TO A REVERSE VENDING MACHINE IN STORE, (2) REMOVAL OF (A) EXISTING ENTRANCE/EXIT POD AND (B) EXISTING TROLLEY BAY, (3) PROPOSED (A) FREE STANDING TROLLEY BAY AND (B) ALTERATION WORKS TO STORE ELEVATION AND (4) ALTERATION WORKS TO CAR PARK AREA AND ALL ANCILLARY WORKS REQUIRED TO COMPLETE TO THE REQUIRED BUILDING REGULATIONS STANDARDS

  1. 24 Nov 2022Received
  2. 19 Jan 2023Conditional
  3. 22 Feb 2023Final approval
  4. 2 Aug 2023Building started
  5. 21 Feb 2024Signed off

Planning details

Status
Building started
Decision
Conditional · 19 Jan 2023
Reference
2251893
Received
24 Nov 2022
Site
320 m²

11 other applications within 500 m in the last year · 1 open for comments

Get the full report

Nearby 11 · 500 m · 12 months

Distance
Time
Show all 11

Explore this area on the map →

Homes nearby

Building started

  • 2 Aug 2023 · Builder told the council work was starting CN0103840DL

Not held yet for Donegal County Council: zoning.

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

2251893 is a planning application to Donegal County Council for modifications to the ground floor layout and shop facade to include the following: (1), received on 24 Nov 2022; permission was granted with conditions on 19 Jan 2023.