Donegal County Council · 2350442
Ballysaggart, St Johns Point Dunkineely, Lifford PO
Approved in May 2023. Building started.
- 4 Apr 2023Received
- 25 May 2023Conditional
- 28 Jun 2023Final approval
- 19 Dec 2023Building started
- 27 Jun 2028Approval runs out
- Status
- Building started
- Decision
- Conditional · 25 May 2023
- Council
- Donegal County Council
- Type
- RETENTION
- Site
- 7,453 m²
What’s proposed
EXISTING ROOF WITH INCREASED RIDGE HEIGHT AND PERMISSION FOR (1) EXTENSION AND RENOVATION TO EXISTING DWELLING WITH ALTERATIONS TO ALL FACADES, (2) INSTALLATION OF A NEW SEWERAGE TREATMENT SYSTEM AND ALL ASSOCIATED SITE DEVELOPMENT WORKS
Planning details
- Reference
- 2350442
- Local authority
- Donegal County Council
- Status
- Commenced · register status “APPLICATION FINALISED”
- Received
- 4 Apr 2023
- Observations close
- 9 May 2023 (closed 1259 days ago)
- Decision due
- 29 May 2023 · decided 25 May 2023
- Decision
- Conditional on 25 May 2023
- Site area
- 7,453 m² from the mapped boundary, not the council's figure
Nearby 6 · 500 m · 5 years
- GrantedBALLYSAGGART , ST. JOHNS POINT , DUNKINEELY
- WithdrawnBALLYSAGGART , ST. JOHN'S POINT , DUNKINEELY DONEGAL PO
- WithdrawnBALLYSAGGART , ST. JOHN'S POINT , DUNKINEELY DONEGAL PO
- GrantedBALLYSAGGART , ST. JOHN'S POINT , DUNKINEELY
- Appeal decidedBALLYSAGGART TD AND BALLYEDERLAN TD , DUNKINEELY , DONEGAL PO
- GrantedBALLYSAGGART , ST. JOHNS POINT , DUNKINEELY
Homes nearby
Building started
- 19 Dec 2023 · Builder told the council work was starting (opted out of the finish sign-off) CN0108263DL
Not held yet for Donegal County Council: zoning.
Protections nearby 250 m
- NIAH-recorded building · 1
- Recorded monument · 5
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
2350442 is a planning application to Donegal County Council for existing roof with increased ridge height and permission for (1) extension and, received on 4 Apr 2023; permission was granted with conditions on 25 May 2023.