Approved in Jan 2024. Building started in 2024.

  1. 11 Apr 2023Received
  2. 7 Dec 2023Conditional
  3. 19 Jan 2024Final approval
  4. 10 Apr 2024Building started

Planning details

Status
Building startedi
Decision
Conditional · 7 Dec 2023
Reference
2350469
Received
11 Apr 2023
Further information
Requested 1 Jun 2023 · received 11 Oct 2023
Units
1
Site
5,309 m²

What’s proposed

CONSTRUCTION OF A DWELLING HOUSE, DOMESTIC GARAGE, WASTE WATER TREATMENT SYSTEM AND ALL ASSOCIATED SITE WORKS

3 other applications within 500 m in the last year

Open the report

Nearby 3 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Building started

  • 10 Apr 2024 · Builder told the council work was starting (opted out of the finish sign-off) CN0112215DL

Not held yet for Donegal County Council: zoning.

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary